GCT Deltaport Expansion - Berth Four Project

GCT Canada Limited Partnership is proposing to expand its existing GCT Deltaport Container Terminal, a container storage and handling facility located in Delta, British Columbia, approximately 35 kilometres south of Vancouver. As proposed, the GCT Deltaport Expansion - Berth Four Project would add a fourth berth on the east side of the Roberts Bank Causeway, include an expansion of the intermodal rail yard along the causeway (Roberts Bank Way) and dredging to provide safe access for ships. The additional land-based container storage and handling facilities would provide an additional two million 20-foot long storage containers (otherwise referred to as 20-foot equivalent units or TEUs) per year at the existing terminal.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Latest update

May 31, 2022 — The Impact Assessment Agency of Canada has posted the Notice of Commencement of an Impact Assessment and issued the Joint Impact Statement Guidelines and required plans to the proponent for the preparation of an Impact Statement.
 

May 16, 2022 — The Impact Assessment Agency of Canada has resumed the limit for the planning phase of the impact assessment.

Participate

Key documents

Key documents
Document Number Document Title File Date
223 Summary of Federal Incidental Activities and Provincial Required Assessment Matters Analysis for the GCT Deltaport Expansion - Berth Four Project PDF (222 KB) June 30, 2022
217 GCT Deltaport Expansion, Berth Four Project - Joint Indigenous Engagement and Partnership Plan Graphic JPG (9.7 MB) June 3, 2022
210 Notice of Commencement of an Impact Assessment - May 31, 2022
209 Joint Permitting and Regulatory Coordination Plan PDF (763 KB) May 31, 2022
208 Joint Indigenous Engagement and Partnership Plan PDF (5.2 MB) May 31, 2022
207 Joint Assessment Plan PDF (608 KB) May 31, 2022
206 Joint Guidelines PDF (2.9 MB) May 31, 2022
202 Notice of Time Limit Resuming - May 16, 2022
201 From GCT Canada Limited Partnership to the Impact Assessment Agency of Canada re: Withdrawal of Short Sea Shipping as a project component of the GCT Deltaport Expansion - Berth Four Project PDF (759 KB) May 4, 2022
191 Notice of Time Limit Suspension with Reasons - March 31, 2022
95 Agency and EAO joint presentation from December 2021 Virtual Information Sessions (see Reference #86) PDF (13 MB) December 2, 2021
76 Notice of Referral to Review Panel - November 3, 2021
72 Notice of Impact Assessment Decision with Reasons - October 28, 2021
71 Summary of the Detailed Project Description (see reference #201) PDF (7.3 MB) October 28, 2021
70 Detailed Project Description (see reference #201) PDF (17 MB) October 28, 2021
61 Joint Summary of Issues and Engagement PDF (728 KB) December 23, 2020
1 Initial Project Description of a Designated Project PDF (9.8 MB) September 18, 2020

List all records

Contacts

GCT Deltaport Expansion - Berth Four Project
Impact Assessment Agency of Canada
160 Elgin Street
22nd Floor
Ottawa, Ontario K1A 0H3
Telephone: 343-572-7144
Email: deltaport@iaac-aeic.gc.ca


  • Location

    • Delta (British Columbia)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    In progress
  • Start Date

    2020-09-28
  • Proponent

    GCT Canada Limited Partnership
  • Authorities

    • Impact Assessment Agency of Canada
  • Assessment Type

    Impact assessment by Review Panel
  • Reference Number

    81010