Westshore Terminals Berth 2 Mooring Dolphin Upgrades - Second Extension to Expiry Date

Westshore Terminals Limited Partnership proposes to upgrade four (4) existing mooring dolphins (piles) (the "Project") at Berth 2 of its terminal at 1 Roberts Bank, Delta (the "Site"). The Project's schedule is aligned with a materials handling project (PER No. 20-209 available here). Due to delays with the materials handling project, the anticipated completion of the Project has been delayed until the end of 2024. These delays indicate the Project will not be completed prior to February 28, 2024, and therefore an extension to the validity of the permit is needed. There are no changes to construction activities or the scope of the work outlined in the approved permit (available here). 


Latest update

Notice of Determination

Delta, B.C. – December 15, 2022 The Vancouver Fraser Port Authority has determined that the proposed Westshore Terminals Berth 2 Mooring Dolphin Upgrades – Extension to Expiry Date located at 1 Roberts Bank, Delta Canada V4W 4G5 is not likely to cause significant adverse environmental effects.

Participate

Contacts

Project and Environmental Review
Vancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com


  • Location

    • Delta (British Columbia)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    Completed
  • Start Date

    2022-10-12
  • Proponent

    Westshore Terminals Limited Partnership
  • Authorities

    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    80437