Expand Green Fleet Parking - Richmond Armoury

The Department of National Defence (DND) has proposed a project. Parking lot improvements are required to support on-going operations at the Colonel Sherman Armoury. Proposed activities include expansion of the existing parking lot to the north of the armoury building (Lot #1) and the reallocation and improvements of two additional parking lots south of the armoury building (Lot #2 and Lot #3).

Expansion of Lot #1 will include the construction new paved parking lot with a total of 68 parking stalls. Construction of the parking lot will require grubbing and vegetation removal, including the removal of manicured grass, shrubs, and trees. Associated construction activities to accommodate the new parking lot will include removal and installation of curbs, gutters, and sidewalks, installation of new catch basins and utility access holes, concrete works, line painting, signage installation, and irrigation system connection. The anticipated excavation depth during construction is expected to be 500 millimeters and a total construction area of approximately 740 square meters. The total estimated material to be removed during construction is approximately 370 cubic meters for this Lot.

Proposed activities at Lot #2 include the construction of 18 new paved parking stalls. The area is currently occupied by a landscaped area and existing pavement used for non-parking purposes. Associated infrastructure activities will also be completed including but not limited removal of existing asphalt infill, installation of new asphalt surface, adjustment to existing curbs, and changes to drainage infrastructure. The proposed excavation depth is 275 millimeters to the top of the subbase layer (Area 2), and 675 millimeters down to the subbase layer (Area 1). The proposed construction area is approximately 302 square meters and the estimated total material to be removed is approximately 138 cubic meters.

Activities at Lot 3 are proposed to include the removal of existing fence line, removal of existing parking wheel stops (to be re-used in Lot #2) and removal of existing and construction of a new fence line along the south, west and north perimeter of the parking lot. Approximately 138 meters of existing fence will be removed and replaced. The new fence will be of heavy-duty mesh 2.70 meters in height, with an additional 0.30 meters of barbed wires above the top rail, totaling 3.0 meters above ground. The fence post will be buried down to 1.22 meters below ground, which includes the 0.15 meters of concrete footing. The degree of excavation and material removal as the result is expected to be marginal due to the small footprint of the existing fence line.

More


Latest update

August 9, 2023— The Department of National Defence issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination - August 9, 2023
1 Public Comment Period on Intent to Make a Determination - June 30, 2023

Contacts

Angela Manweiler
Department of National Defence
Angela Manweiler, Environment Officer
5535 Korea Road
Chilliwack, British Columbia V2R 5P2
Email: Angela.Manweiler@forces.gc.ca


  • Location

    • Richmond Armoury (British Columbia)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2023-06-30
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    85732
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: