Barge loading facility
The proposed project
In September 2019, the proponent, BD Hall Constructors Corp., submitted a project permit application to construct a shore-access barge loading facility on the north shore of the Fraser River at 2320 Rogers Avenue in Coquitlam, British Columbia. The public was initially invited to submit written comments between October 7 and November 7, 2019. The proponent has since redesigned the project based on feedback from regulators, Indigenous communities, and marine users. As a result, the project summary has been updated and the public is once again invited to submit written comments.
The purpose of the barge loading facility is to load barges with non-contaminated soil for disposal at sea with appropriate permits from Environment and Climate Change Canada. Barges would be up to 18 metres (58 feet) by 73 metres (240 feet) in size. The facility would also be used to import clean gravel. The source and destination sites of the soil and gravel would be various construction properties throughout Metro Vancouver.
The construction works occurring within federal lands include installation of a pile supported barge ramp at the south end of the facility. Land and marine equipment would be used to access and construct at the site. Twenty-two steel piles would be installed with a vibratory hammer on a scow. Eight piles would be used to support barge mooring, four piles to support the head frame, eight piles to support the barge deck and ramp, and two piles within the foreshore to support the barge deck abutment. A prefabricated ramp headframe, prefabricated barge deck, and a prefabricated barge ramp would be installed to piles. The barge ramp and headframe would be equipped with lights and mooring bollards. The proponent will also install habitat improvements along 25 metres of the beach west of the barge ramp to improve riparian and aquatic habitat. These habitat improvements include regrading, strategic placement of rocks, and vegetation planting.
Once constructed, site operations would include upland material storage, trucking of material to and from barges, barge moorage, and barge transportation. It is estimated that one to two barges would be loaded per week for disposal at sea. Vehicle parking, truck staging would not be within federal lands. The barge ramp facility would operate Monday to Saturday between 7:00 a.m. and 8:00 p.m. Approximately 500 trucks per week or 83 trucks per working day, on average, would arrive at the Site during operations.
To help inform a determination on whether the proposed project is likely to cause significant adverse environmental effects, and to assist the Vancouver Fraser Port Authority in making a decision on whether or not to approve the proposed project, the Vancouver Fraser Port Authority and Transport Canada are inviting comments from the public.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
The public comment period on the project is closed. The Vancouver Fraser Port Authority and Transport Canada are considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects. .
List all records
Contacts
Project and Environmental ReviewVancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com
-
Location
- Barge loading facility (British Columbia)
-
Project Type
- Ports and Harbours
- Soil management
-
Status
In progress -
Start Date
2020-11-05 -
Proponent
BD Hall Constructors Corp. -
Authorities
- Transport Canada
- Vancouver Fraser Port Authority
-
Assessment Type
Project on federal lands -
Reference Number
80240
Nearby projects
..within 200 kilometres-
Fraser Mills Pile Removal
Fraser Mills Pile Removal -
Fraser Mills Foreshore Improvements
Fraser Mills Foreshore Improvements -
Osprey Nest Platform
Osprey Nest Platform -
Shoreline protection and retaining wall improvements project
Shoreline protection and retaining wall improvements project -
Georgia Pacific Gypsum Plant Demolition
Georgia Pacific Gypsum Plant Demolition -
Schnitzer Steel Maintenance Dredging
Schnitzer Steel Maintenance Dredging -
Retaining wall replacement
Retaining wall replacement -
Surrey Langley SkyTrain Project and Broadway Subway Project
Surrey -
Lehigh Materials - Surrey Barge Ramp Project
Lehigh Materials - Surrey Barge Ramp Project -
Amix Pile and Float Removal
Amix Pile and Float Removal -
Olsen Road site development for truck staging
Olsen Road site development for truck staging -
Schnitzer Fire Suppression Project - Design Amendment
Schnitzer Fire Suppression Project - Design Amendment -
CN rail bridge seismic retrofit project
CN rail bridge seismic retrofit project -
Fire Hydrant Replacement
Surrey Taxation Data Centre -
Demolition of Office Building and Parking Canopies
Demolition of Office Building and Parking Canopies -
Expansion of the Lumber Transload Facility of Goodrich Terminal2012 Ltd. at the Port of Vancouver
Port of Vancoouver -
Installation of scour protection
Installation of scour protection -
Halo Sawmill Maintenance Dredging
Halo Sawmill Maintenance Dredging -
Rocky Point Park Boat Ramp Repair in Port Moody
Rocky Point Boat Ramp Repair in Port Moody -
Containerized dry bulk handling project
Containerized dry bulk handling project -
Annacis Water Supply Tunnel Safe Havens Amendment
Annacis Water Supply Tunnel Safe Havens Amendment -
Annacis Water Supply Tunnel Safe Havens Amendment
Annacis Water Supply Tunnel Safe Havens Amendment -
Shoreline Protection at 177 Duncan Street in New Westminster
Shoreline Protection at 177 Duncan Street in New Westminster -
Amendment to the construction hours and permit expiry date for the approved Sediment Remediation and Dike Construction
Amendment to the construction hours and permit expiry date for the approved Sediment Remediation and Dike Construction -
Installation of Pole Lights
100 Annacis Parkway, Annacis Island, Delta -
Fraser Grain Terminal - Grain Export Facility - Amendment 06 - Grain Cleaner
Fraser Grain Terminal - Grain Export Facility - Amendment 06 - Grain Cleaner -
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-05 - Amendment (Condition 36 - Extended Hours)
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-05 - Amendment (Condition 36 - Extended Hours) -
WWL Underground Storage Tank Removal Annacis Island
Delta -
Teal-Jones Maintenance Dredging
Teal-Jones Maintenance Dredging -
Pacific Coast Terminals Co. Ltd. Port Moody Channel Dredging Permit Amendment Request
Pacific Coast Terminals Co. Ltd. Port Moody Channel Dredging Permit Amendment Request -
Maintenance Dredging at FRPD Waterlot
Maintenance Dredging at FRPD Waterlot -
Queensgate Maintenance Dredging
Queensgate Maintenance Dredging -
Amendment to the construction hours in respect to condition 45 of the approved Pattullo Bridge Replacement Project (PER No. 17-107)
Amendment to the construction hours in respect to condition 45 of the approved Pattullo Bridge Replacement Project (PER No. 17-107) -
Truck Parking Construction - Nordel Way Area
Truck Parking Construction - Nordel Way Area -
Katzie First Nation Shoreline Clean Up
Pitt Meadows -
Annacis Island Wastewater Treatment Plant New Outfall - Project Permit No. 17-093-1 - Amendment (Condition 32 - Extended Hours)
Delta -
Delta Cedar New Pile Installation
Delta -
Langley Outfall Maintenance Dredging
Langley Outfall Maintenance Dredging -
Vito Shipyards Wharf Repairs
Delta -
Vito Dock Maintenance Dredging
Delta -
Vito Shipyards Wharf Repairs amendment
Vito Shipyards Wharf Repairs amendment -
Shellburn Berthing Dolphin Replacement
Burnaby -
New Pile Installation for Recreational Dock
New Pile Installation for Recreational Dock -
Burnco Langley Maintenance Dredging Project
Burnco Langley Maintenance Dredging Project -
Removal of Concrete Boat Launch
Removal of concrete boat launch -
Stormwater outfall and dike upgrades
Stormwater outfall and dike upgrades -
Trans Mountain Expansion Project
Burnaby -
Cates Park Foreshore Erosion Protection Project
North Vancouver -
Canadian Coast Guard Purfleet Point Front and Rear Range Rebuild
Lower Fraser River of the Vancouver Regional District, New Westminster, Annacis Island, British Columbia -
Barge Ramp Beam Installation
Burnaby -
Canadian Coast Guard Purfleet Point Front and Rear Range Rebuild
Lower Fraser River of the Vancouver Regional District, New Westminster, Annacis Island, British Columbia -
Installation of Eight Steel Pipe Piles - Project Permit No. 18-184 - Extension to the Expiry Date
Burnaby -
Golden Ears Forcemain (GDEFM) Project
Golden Ears Forcemain Project -
Installation of non-hydraulic boat lift
Installation of non-hydraulic boat lift -
New Float Installation for 2250 Farrer Cove Place
Public Notice New Float Installation for 2250 Farrer Cove Place -
Existing Dock Upgrade for 4659 Strathcona
Existing Dock Upgrade for 4659 Strathcona -
City of Delta Stormwater Outfall
City of Delta Stormwater Outfall -
District of North Vancouver Designated Anchorage Area
District of North Vancouver Designated Anchorage Area -
Chemtrade maintenance dredging
Chemtrade maintenance dredging -
Water Supply Tunnel at Second Narrows - Metro Vancouver - Amendment
Water Supply Tunnel at Second Narrows - Metro Vancouver - Amendment -
Delta Grinding Facility Project
Tilbury Island, Delta -
Installation of Annex 4 Vacuum System
Installation of Annex 4 Vacuum System -
Fraser River Pile and Dredge No. 8 Road Barge Ramp Maintenance Dredging
Richmond -
Rail Expansion with Tent
Rail Expansion with Tent -
Tilbury Phase 2 LNG Expansion Project
Tilbury Island, Delta -
Site Upgrades and Road Realignment - Lynnterm - Project Permit No. 17-154-2 - Extension to the Expiry Date
Site Upgrades and Road Realignment - Lynnterm - Project Permit No. 17-154-2 - Extension to the Expiry Date -
Surrey Langley SkyTrain Project and Broadway Subway Project
Langley -
WesPac Tilbury Marine Jetty Project
Tilbury Island, Delta -
Oil Spill Emergency Response Base - Project Permit No. 16-290 - Extension to the Expiry Date
Vancouver -
Cascadia West Rail Extension
Vancouver -
South Shore Corridor Project - Extension to Expiry Date
South Shore Corridor Project - Extension to Expiry Date -
G3 Terminal Vancouver - G3 Limited - Project Permit No. 15-180 - Extension to the Expiry Date and Extended Work Hours
G3 Terminal Vancouver - G3 Limited - Project Permit No. 15-180 - Extension to the Expiry Date and Extended Work Hours -
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01 -
G3 Terminal Vancouver Berth Pocket Obstruction Removals
G3 Terminal -
Columbia Containers Shoreline Protection Repair
Columbia Containers Shoreline Protection Repair -
Pacific Elevators New Dust Control System and Access
Pacific Elevators New Dust Control System and Access -
Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080)
Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080) -
Extension - Temporary Construction Staging Parking and Barge Loading
Extension - Temporary Construction Staging Parking and Barge Loading -
Mariner Seafoods Shoreline Protection
Mariner Seafoods Shoreline Protection -
Neptune Terminal maintenance dredging at Berth 2 and 3
Neptune Terminal maintenance dredging at Berth 2 and 3 -
Maintenance Dredging, Fraser River, Small Craft Harbours
Kanaka Landing -
Marine Operations Facility
Marine Operations Facility -
Neptune - Rail Bypass Track Layout
Neptune - Rail Bypass Track Layout -
Dust Suppression Upgrade - Neptune Bulk Terminals (Canada) Ltd. - Project Permit 16-072 - Extension to the Expiry Date
Dust Suppression Upgrade - Neptune Bulk Terminals (Canada) Ltd. - Project Permit 16-072 - Extension to the Expiry Date -
Pacific Terminals Emergency Vehicle Road Access
Pacific Terminals Emergency Vehicle Road Access -
Pacific Terminals Annex 1 and 2 Vacuum System Upgrade
Pacific Terminals Annex 1 and 2 Vacuum System Upgrade -
Neptune Cargill Overpass Extension - Project Permit No. 17-131-1 - Amendment (Condition 17 - Extended Hours)
North Vancouver -
Water Supply Pipe and Casing - Neptune
Water Supply Pipe and Casing - Neptune -
Dredging to Deepen Berth 1 - Project Permit No. 18-027-1 - Amendment (Condition 23 - Extended Hours)
North Vancouver -
Neptune Coal Capacity Project and West Quadrant Shiploader - Project Permit No. 12-066-1 - Amendment (Condition 18 - Extended Hours)
North Vancouver -
Extension to expiry date of Project Permit No. 18-027: Dredging to deepen berth 1 at Neptune Bulk Terminals
Extension to expiry date of Project Permit No. 18-027: Dredging to deepen berth 1 at Neptune Bulk Terminals -
Global Container Terminal Vanterm Maintenance Dredging
Vancouver -
Maintenance Dredging, Fraser River, Small Craft Harbours
McMillan Island Harbour -
Amendment to dates - Centerm Expansion Project Fisheries Act Authorization
Vancouver -
Centerm Expansion Project - Amendment to Fisheries Act Authorization
Vancouver -
Centerm Expansion Project - Amendment PER No. 15-012-03 (Condition 47 - Extended Hours)
Centerm Expansion Project - Amendment PER No. 15-012-03 (Condition 47 - Extended Hours) -
Maintenance dredging - Centerm
Maintenance dredging - Centerm -
Seabin Installation at Main Street Dock
Vancouver, British Columbia -
Centerm Expansion Project - Amendment (Condition 66 - Dredging)
Centerm Expansion Project - Amendment (Condition 66 - Dredging) -
Construct Maintenance Building and Military Vehicle Parking at Richmond Armoury
Richmond Armoury, 5500 #4 Road, Richmond -
Fenceline Construction and Maintenance at Richmond Training Area
Colonel Sherman Armoury and Richmond Training Area -
SeaBus Terminal Upgrades (Utilities)
SeaBus Terminal Upgrades (Utilities) -
Nanaimo Vancouver Passenger Only Ferry Service - South SeaBus Terminal - Project Permit No. 18-044-02 - Extension to the Expiry Date
Nanaimo Vancouver Passenger Only Ferry Service - South SeaBus Terminal - Project Permit No. 18-044-02 - Extension to the Expiry Date -
Flood Barrier
Vancouver -
Vancouver Airport Fuel Delivery Project
Richmond -
Concrete Batch Plant
Vancouver -
Kings Mill Park Shoreline and Habitat Work
Kings Mill Park Shoreline and Habitat Work -
Subtidal Cobble Replacement
North Vancouver -
Seaspan Ship Load-out Gravel Bed and Shoreline Protection
North Vancouver -
Seaspan Outfitting Pier Extension
Seaspan Outfitting Pier Extension -
Fibreco Terminal Enhancement Project Amendment (Stormwater Design)
North Vancouver -
Maintenance Dredging, Fraser River, Small Craft Harbours
McIvors Landing -
Royal Vancouver Yacht Club (RVYC) Coal Harbour Marina Expansion
Royal Vancouver Yacht Club (RVYC) Coal Harbour Marina Expansion -
Kitsilano CCG SAR - Workshop Reconstruction
Kitsilano CCG SAR -
Riparian Habitat Enhancement - Russ Baker Way Lands
Riparian Habitat Enhancement - Russ Baker Way Lands -
New Microwave system and antenna proposal at 1959 Marine Dr. North Vancouver, BC
1959 Marine Drive North Vancouver BC -
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours)
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours) -
Conveyance for North Shore Wastewater Treatment Plant - Project Permit No. 17-090-1 - Amendment (Condition 51 - Extended Hours)
North Vancouver -
Maintenance Dredging, Fraser River, Small Craft Harbours
Whonnock Harbour -
Steveston Paramount Maintenance Dredging
Steveston Paramount Small Craft Harbour -
Drainage Maintenance and Improvement Project - Alaksen National Wildlife Area
Alaksen National Wildlife Area -
Metro Vancouver - Conveyance for North Vancouver Wastewater Treatment Plant Amendment
Metro Vancouver - Conveyance for North Vancouver Wastewater Treatment Plant Amendment -
Pacific Enterprise Science Centre (PESC) Foreshore Maintenance
Pacific Enterprise Science Centre (PESC) -
GCT Deltaport Expansion - Berth Four Project
Delta -
Roberts Bank Terminal 2 Project
Delta -
Westshore Terminals Berth 2 Mooring Dolphin Upgrades
Delta -
Replacement of the Aldergrove Weather Radar
26600 8th Avenue, Langley, BC V0X 1A0 -
Maintenance Dredging, Fraser River, Small Craft Harbours
Mission Harbour -
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities)
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities) -
Sumas IR6 Former Brick Plan Demolition and Remediation
Sumas First Nation Indian Reserve 6 -
Winter Cove Boat Ramp Repair, Saturna Island
Gulf Islands National Park Reserve -
Gibsons Small Craft Harbour Wharf Reconstruction
Gibsons Landing Small Craft Harbour -
Nav Canada surveillance radar - Gulf Islands National Park Reserve, Saturna Island, BC
Saturna Island, BC - Gulf Islands National Park Reserve of Canada -
BURNCO Aggregate Mine Project
Howe Sound -
Woodfibre LNG Project
Howe Sound -
Radio Tower Upgrades, North Pender Island
Gulf Islands National Park Reserve -
Freedom Mobile Installation on Radio Tower Site, North Pender Island
Gulf Islands National Park Reserve -
WildFire Risk Reduction Project - fuels managment at three sites in Gulf Islands National Park Reserve
Gulf Islands National Park Reserve -
Telus Communications Inc. Radiocommunication Antenna Addition on Sechelt Band Lands No 2 Reserve, Sechelt BC
5411 Reservoir Road Sechelt BC, Sunshine Coast area on the Sechelt Band Lands No 2 Reserve -
SAY Community Centre
Skowkale No. 10 Reserve Land -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Bivouac Site, OPSEE Training Area
OPSEE Training Area, Vance road, Cultus Lake -
Porpoise Bay Harbour Boat Grid Removal
Porpoise Bay Harbour -
Sidney Spit Buoy Upgrades
Gulf Islands National Park Reserve -
Campground Kiosk Install
Gulf Islands National Park Reserve -
Establishing Shrubs in Protective Fenced Areas to Facilitate Forest Restoration on Sidney Island
Gulf Islands National Park Reserve -
Control of English Hawthorn on Sidney Island
Gulf Islands National Park Reserve -
GRT Holdings Ltd. Construction and Operation of Soil Treatment Facility -DUKE POINT
Nanaimo -
Construction of a Distribution Warehouse
Victoria International Airport -
Blue Heron Aeropark Construction of Aircraft Hangars
Victoria International Airport YYJ -
Western Canadian Marine Response Corporation (WCMRC) Saanich Base
Victoria International Airport (YYJ) -
Titan Boats Construction of a Boat Manufacturing Facility
Victoria International Airport (YYJ) -
Temporary Installation of Remotely Piloted Aircraft System (RPAS) Detection Equipment
Victoria International Airport -
Modification of Existing Petroleum Storage Facility
Victoria International Airport -
Institute of Ocean Sciences Patricia Bay - Wharf Waterline Replacement
The Institute of Ocean Sciences is located in Sidney BC. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Institute of Ocean Sciences Patricia Bay - Wharf refurbishment
The Institute of Ocean Sciences is located in Sidney BC, on Vancouver Island. The facility is accessible via road access, as well as by water. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Institute of Ocean Sciences Patricia Bay - Miscellaneous Repairs 2020
The Institute of Ocean Sciences is located in Sidney BC. The facility is accessible via road access, as well as by water for vessel/barge access. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Site preparation for a subdivision on Popkum IR 2
Popkum IR2 -
Seabird Island Cultural Education, Community Resource Centre and Long-House Project
Agassiz, British Columbia -
WCMRC Oil Spill Response Facility at Nanaimo Harbour
Nanaimo -
WCMRC Oil Spill Response Facility at Nanaimo Harbour
Nanaimo -
Pauquachin Legacy Gathering Space
Cole Bay No. 3 Reserve (Pauquachin First Nation), North Saanich BC -
Exterior Landscape Redesign
60 Front Street Nanaimo -
Nanaimo to Protection Island Submarine Cable Replacement Project
Nanaimo -
Shxw'owhámél First Nation Outdoor Recreation Infrastructure Project
Shxw'owhámél First Nation -
Install Security Cameras at Winchelsea Island
Winchelsea Island, which is part of the Canadian Forces Maritime Experimental Test Ranges (CFMETR), in Nanoose Bay -
Construction of a Boat Storage Facility at Colwood, CFB Esquimalt
CFB Esquimalt's Colwood property, located in the municipality of Colwood. -
Pedestrian Walkway Extension Lot B1
Esquimalt Graving Dock -
Replacement and Installation of New Base Security Cameras - Colwood and Naden, Canadian Forces Base (CFB) Esquimalt
CFB Esquimalt Naden property, located in Victoria -
EastEnd Dock Extension-Dock Floor/Wall Refurbishment
Esquimalt Graving Dock -
Replacement and Installation of New Base Security Cameras - Colwood and Naden, Canadian Forces Base (CFB) Esquimalt
CFB Esquimalt Colwood property, located in Victoria -
G Jetty and Jetty 11 Remediation in Esquimalt Harbour
Colwood, Esquimalt Harbour, located in the municipality of Colwood British Columbia -
Victoria Coast Guard Base - Timber Fender Replacement
This project is located on the wharf at the Victoria Coast Guard Base, 25 Huron Street, Victoria, BC. The base is accessible via road access, as well as by water for vessel and barge access. -
Colwood Fuel Oil Depot - Air Scrubber
Colwood Fuel Oil Depot, Rosebank Road, Colwood -
Canadian Coast Guard Victoria Base Wharf Refurbishment
The Victoria Coast Guard Base in James Bay, Victoria, British Columbia. The base is situated 2km from downtown Victoria, and lies on the edge of the Victoria's inner harbour, which eventually funnels out into the Strait of Juan de Fuca. -
Canadian Coast Guard Victoria Search and Rescue Float
25 Huron Street, Victoria BC, V8V 4V9 -
Drydock Leak Repairs at HMC Dockyard, Canadian Forces Base Esquimalt
Her Majesty's Canadian Dockyard, Esquimalt Harbour -
Royal Roads University - Japanese Gardens Drainage Upgrades
Royal Roads University, 2005 Sooke Road, Colwood -
Royal Roads University Sustainability Initiative - Overhead Service Upgrades (Lower Campus)
Royal Roads University in Colwood -
Royal Roads University Recreation Centre Change Room Renovation Project
Royal Roads University campus, in the municipality of Colwood, British Columbia -
CREST - Microwave dish and VHF antenna - Mary Hill and Albert Head Road, Metchosin British Columbia
Albert Head Road, Metchosin -
Yale First Nation Recreation Centre
Stulkawhits No. 8 Reserve Land -
CREST - Microwave dish and VHF antenna - Mary Hill and Albert Head Road, Metchosin British Columbia
Mary Hill - 5300 William Head Road, Metchosin -
Canadian Forces Ammunition Depot (CFAD) Rocky Point Main Gates Recapitalization
CFAD Rocky Point, located in the municipality of Metchosin, BC. -
Connect Municipal Water Supply to Canadian Forces Ammunition Depot (CFAD) Rocky Point
Canadian Forces Ammunition Depot (CFAD) Rocky Point , Metchosin -
City of Powell River - Consolidated Waste Water Treatment Project
Powell River -
TOPAZ Submarine fibre-optic cable
Port Alberni -
N'Quatqua Multi-Use Facility Project
N'Quatqua Multi-Use Facility Project -
Raven Underground Coal Mine Project
Buckley Bay -
Canadian Coast Guard - Cape Lazo BC - Oceans Protection Plan - Marine Safety System Modernization Initiative
Cape Lazo -
Kingsvale-Oliver Reinforcement Project
Kingsvale -
Kwispaa LNG Project
10 kilometres northeast of Bamfield -
Lower Nicola Indian Band Community Solar Gardens
Lower Nicola Reserve Lands - Nicola Mameet No. 1, Joeyaska No. 2, and Zoht No. 4 -
Contaminated Site Remediation: Grice Bay and McLean Point
Pacific Rim National Park Reserve