Installation of an Outfall Pipeline, Mortier Bay, NL

Grieg NL Nurseries Ltd. is proposing to install a 150mm high-density polyethylene (HDPE) outfall pipeline from their land-based aquaculture facility, extending 175m into Mortier Bay, NL. Armour stone protection will be placed on approximately 75m of the pipeline from the shoreline and the remaining 100m of pipeline will be secured to concrete ballast blocks placed every 3m on the sea floor. A workboat with a crane will be used for the installation. The total estimated project footprint will be 1058 m2 below the high-water mark.


Latest update

October 23, 2025  – Transport Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects. 

This determination was based on a consideration of the following factors:

  • Impacts on rights of Indigenous peoples;
  • Community and Indigenous knowledge;
  • Comments received from the public; and
  • Application of technically and economically feasible mitigation measures (including but not limited to those listed in the attached document).

Participate

Key documents

Key documents
Document Number Document Title File Date
3 Valued Environmental Components and Mitigation Measures PDF (136 KB) October 23, 2025
2 Notice of Determination - Installation of Outfall Pipeline, Mortier Bay, NL PDF (120 KB) October 23, 2025
1 Installation of Outfall Pipeline, Mortier Bay, NL PDF (103 KB) August 27, 2025

Contacts

Transport Canada
Melissa Ginn, Regional Environmental Advisor
10 Barter's Hill
St. John's, Newfoundland and Labrador A1C 6M1
Telephone: 709-351-3200 or 1-888-675-6863
Email: melissa.ginn@tc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Outfall Pipeline, Mortier Bay, NL (Newfoundland and Labrador)
  • Nature of Activity

    • Water Management
  • Assessment Status

    Completed
  • Start Date

    2025-08-27
  • Proponent

    Grieg NL Nurseries Ltd
  • Authorities

    • Transport Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    89853