St. John's Small Concrete Dam Removal Project
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Project Description:
Agriculture and Agri-Food Canada intends to remove a small concrete dam on Flings Brook at the St. John's Research and Development Center. This dam was used as a reservoir for fire suppression on the site and is recommended for removal due to it's degraded condition. The water supply for fire suppression has long been transferred to municipal water, so the dam is no longer required.
Latest update
The authority issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination | - | May 1, 2025 |
| 1 | Public Comment Period on Intent to Make a Determination | - | March 26, 2025 |
Contacts
Environmental Management ServicesAgriculture and Agri-Food Canada
Building 12, Central Experimental Farm
960 Carling Avenue
Ottawa, Ontario K1A 0C5
Email: aafc.EnvMgtServices-Servicesgestionenv.aac@agr.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- St. John's (Newfoundland and Labrador)
-
Nature of Activity
- Dams and reservoirs
-
Assessment Status
Completed -
Start Date
2025-03-26 -
Proponent
Agriculture and Agri-Food Canada -
Authorities
- Agriculture and Agri-Food Canada
-
Assessment Type
Project on federal lands -
Reference Number
89393
Nearby assessments
...within 200 kilometres-
St. John's AAFC Research and Development Centre Waterline Upgrade Project
St. John's -
St. John's Building Retrofit Project
St. John's -
Completion of Route 3
Mount Pearl -
Government of Canada Building Construction in St. John's, NL
80 Kelsey Drive, St. John's, Newfoundland. -
Sediment Removal Under Syncrolift 2023
St. John's Dockyard Limited (NEWDOCK) -
Canadian Coast Guard Demolition of Administration Building, Southside Road, St. John's, NL
Southside Road, St. John's, NL -
Phase 1 of the Riverhead Wastewater Treatment Facility: Secondary Treatment Expansion Project
St. John's -
Proposed Removal and Relocation of Sediment at Piers 10 and 11 (St. John's Harbour)
Piers 10 and 11 (St. John's Harbour) -
Pier 23 Upgrade – St. John's Harbour Terminal
Pier 23 - St. John's Harbour Terminal -
Sir Humphrey Gilbert Building Radar Communications Site
Sir Humphrey Gilbert Building -
Wharf Replacement Pier 20 West and Pier 21
Pier 20/21 -
Steel Sheet Pile Wall Repairs St. John's Dockyard Limited
St. John's Harbour -
Proposal Removal and Relocation of Sediment within the Navigation Channel (St. John's Harbour)
Navigation Channel -
Breakwater Construction at Petty Harbour SCH, NL
Petty Harbour SCH is located in the community of Petty Harbour, Newfoundland. Located in the Avalon Peninsula, east of St. John’s, NL. -
New Trail Exit Construction
St. John's, Newfoundland -
Perimeter Ditching and Site Drainage Improvements
East White Hills -
Portugal Cove Light and Fog Signal Replacement
Portugal Cove -
Installation of Septic Field
Cape Spear National Historic Site -
Main Electrical Feed Replacement
Cape Spear National Historic Site -
Robin Hood Bay Radar Communications Site
Sugar Loaf Road, Robin Hood Bay, St. John's, NL -
Material Lay-down Area
St. John's -
Wharf Reconstruction, St. Phillip's, Newfoundland
St. Phillip's -
Long Pond Development Project
Conception Bay South -
Torbay Wharf Reconstruction
The Torbay SCH is a located on the eastern side of Newfoundland's Avalon Peninsula. -
Interior & Exterior Upgrades to Facility
Bell Island -
Shoreline Protection, Flatrock, NL
The DFO-SCH project site is located in Flatrock, Newfoundland. -
Chapel's Cove Breakwater Mitigation Project
Town of Harbour Main - Chapel's Cove-Lakeview -
Harbour Redevelopment at Ship Cove SCH, NL
Ship Cove SCH is located in Port de Grave, Newfoundland. Port de Grave is located along the shore of Conception Bay, in the Avalon Peninsula. -
Holyrood District Office & Detachment Re-grading and Re-surface of Parking Lot
36-40 Salmonier Line -
Marginal Wharf Reconstruction, Port de Grave, Newfoundland
Port de Grave -
Sanitary and Storm Sewer Outfall Relocation
Harbour Grace -
Wharf Reconstruction, Harbour Grace, Newfoundland
Harbour Grace -
DFO-SCH Shoreline Restoration / Armourstone Installation, Harbour Grace, NL
Harbour Grace -
Repair, regrade and resurfacing parking lot - Bay Roberts Detachment
Bay Roberts -
Warehouse Water and Sewer Servicing at Tilton Barrens, NL
The Tilton Barrens is a DFO property located at 899 Conception Bay Highway, Tilton, Newfoundland (NL). -
Wharf Reconstruction, Carbonear, Newfoundland
Carbonear -
Cambrai Rifle Range Repair – Canadian Forces Station St. John's
Canadian Forces Station St. John’s -
Wharf Reconstruction and Breakwater Extension, Ochre Pit Cove, NL
Ochre Pit Cove, Newfoundland -
Floating Dock construction, Whiteway, NL
DFO SCH Site in Whiteway, NL (DFRP # 00158) -
Main Beach Armour Stone
Old Perlican -
Bay de Verde SCH Southern Breakwater Extension
The Bay de Verde SCH is an incorporated town in Conception Bay on the northern tip of the Bay de Verde Peninsula of Newfoundland and Labrador. -
Wharf Construction, Bay de Verde, Newfoundland
Bay de Verde -
Wharf Reconstruction, Winterton, Newfoundland
Winterton -
Wharf Reconstruction, Old Perlican, NL
The DFO-SCH project site is located in Old Perlican, Newfoundland. -
DFO-SCH Finger Pier Extension, Old Perlican, NL
Old Perlican -
Wharf Reconstruction - Gooseberry Cove, Newfoundland
Gooseberry Cove -
Wharf Construction, Riverhead, NL
Riverhead, Newfoundland -
North East Arm Camp Hazardous Material Removal and Demolition
The Northeast Arm River is a scheduled salmon river that supports a recreational salmon fishery. The proposed project location is in the North East Arm Camp, accessible via Highway 100 in Dunville, Newfoundland. -
Marginal Wharf Construction, Little Heart's Ease, NL
Little Heart's Ease, Newfoundland -
Newman Sound Day Use Area, HV cable replacement
Terra Nova National Park of Canada -
Cooper Cove Marine Terminal Expansion Project
Placentia Bay -
Finger Pier Reconstruction, Arnold's Cove, NL
Arnold's Cove -
Boat Launch Reconstruction, Arnold's Cove, NL
The DFO-SCH project site is located in Arnold's Cove, Newfoundland. -
Floating Dock Installation, Arnold's Cove, NL
Arnold's Cove, Newfoundland -
Wharf Reconstruction, Jerseyside, Newfoundland
Jerseyside -
Argentia Inspection Station - Roof Replacement
Argentia -
DFO-SCH New Marginal Wharf and Floating Docks, Hickman's Harbour, NL
Hickmans Harbour -
Cape Race Building Demolition
Cape Race -
Wharf Repairs, Portugal Cove South, NL
The DFO-SCH project site is located in Portugal Cove South, Newfoundland. -
Boat Launch Construction, Trepassey, NL
Trepassey, Newfoundland -
Bristy Cove Bridge Rehab
The project is located at Bristy Cove River in the community of Trepassey along the road to Cape Race. -
Utility pole installation along the Bell Aliant fibre optic line in Terra Nova National Park
Terra Nova National Park -
Dredging Branch, NL
Branch -
Breakwater Construction, Summerville, N.L.
Summerville, NL -
Shoreline Protection, St. Bride's, NL
The DFO-SCH project site is located in St. Bride's, Newfoundland. -
Wharf Reconstruction at St. Bride's SCH, Newfoundland and Labrador
The St. Bride's SCH is located within St. Bride's, on the southwestern shore of the Avalon Peninsula, NL. -
Wharf Reconstruction, Bonavista, NL
The DFO-SCH project site is located in Bonavista, Newfoundland. -
Demolition of Cape Bonavista Loran A Site, Bonavista, Newfoundland and Labrador
The Cape Bonavista Loran A site was a long-range radio navigation station located approximately five kilometers north of Bonavista, Newfoundland and Labrador (NL) between Cape Shore Road to the West and the shoreline of Cape Bonavista to the East -
Cape Bonavista Tower Replacement
The DFO-RPSS project site is located in Cape Bonavista, Newfoundland. -
Capital work at the Port Blandford Marina
Town of Port Blandford -
Construction of a mountain bike skills trail in Newman Sound, Terra Nova National Park
Terra Nova National Park of Canada -
Water and Sewer Utility Systems Recapitalization - Phase 2
Terra Nova National Park -
Entrance Washrooms Sanitary Rehabilitations
Terra Nova National Park -
Water Withdrawal from Northwest River, Terra Nova National Park, for Golf Course Irrigation
Terra Nova National Park -
Routine Vegetation Maintenance at Terra Nova Golf Resort and Community
Terra Nova National Park -
Vegetation Maintenance along the Bell Aliant Fibre Optic Line
Terra Nova National Park -
Water and Sewer Utilities System Recapitalisation - Phase 3
Terra Nova National Park -
Fishway Refurbishment, Lower Terra Nova River, NL
The DFO-RPSS project site is located in Terra Nova, Newfoundland. -
Lauchway Reconstruction, St. Bernard's, NL
The DFO-SCH project site is located in St. Bernard's, Newfoundland. -
Fishway Refurbishment, Middle Brook, NL
Middle Brook, Newfoundland -
Helicopter Pad Replacement, Puffin Island, NL
The DFO-RPSS project site is located on Puffin Island, Bonavista Bay, Newfoundland. -
Puffin Island Fuel Tank Replacement
Puffin Island, Bonavista Bay, NL -
Greenspond SCH Wharf Reconstruction
The Greenspond SCH is located on the island of Greenspond, within Bonavista North, in Bonavista Bay, on the northeast coast of the Island of Newfoundland. -
Installation of an Outfall Pipeline, Mortier Bay, NL
Outfall Pipeline, Mortier Bay, NL -
Aid to Navigation Tower Refurbishments - Coast of Newfoundland
Coast -
Marbase Lumpfish Hatchery - Saltwater Intake and Discharge Pipelines, Marystown, NL
Marystown -
Marystown RCMP Detachment Replacement Project
Marystown -
Floating Dock Reconstruction, Wesleyville (Brookfield), NL
Wesleyville -
Wharf Demolition, Burin, NL
The DFO-RPSS project site is located in Burin, Newfoundland. -
Burin Search and Rescue Wharf Construction
Canadian Coast Guard Search and Rescue Station, Burin -
Lauchway Reconstruction, Burin, NL
The DFO-SCH project site is located in Burin, Newfoundland. -
Interior & Exterior Upgrades to Facility
New Wes Valley -
Wharf Reconstruction, Belleoram, Newfoundland
Belleoram -
Wharf Extensions, Pool's Cove, NL
The DFO-SCH project site is located in Pool's Cove, Newfoundland. -
Gander Very High Frequency Omni-directional Range (VOR) Replacement
Gander -
Comfort Cove Building Demolition
Comfort Cove