Torbay Wharf Reconstruction
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The proposed project at Torbay SCH includes the demolition and reconstruction of the existing wharf. The existing wharf structure consists of a concrete spray wall and a timber crib work wharf, both of which are attached to the wharf structures directly adjacent. The concrete spray wall and the existing wharf will be detached from the adjoining structure and then demolished. The new wharf will include the addition of a wharf extension constructed within the existing wharf's footprint with a slight turn south.
Latest update
September 23, 2025 – The federal authorities have issued their Notice of Determination after evaluation of the Wharf Reconstruction at Torbay SCH and have determined that the project is not likely to cause significant adverse environmental effects and can therefore proceed.
This determination was based on a consideration of the following factors:
- Impacts on rights of Indigenous peoples;
- Community and Indigenous knowledge;
- Comments received from the public; and
- Technically and economically feasible mitigation measures.
Mitigation measures taken into account for this determination are:
- To minimize the possibility of fish habitat contamination and the spread of aquatic invasive (alien) species, all construction equipment which will be immersed into the water or has the possibility of coming into contact with such water during the course of the work, must be cleaned and washed to ensure that they are free of marine growth and alien species.
- Weather conditions are to be assessed on a daily basis to determine the risk of extreme weather in the project areas. Avoid work during periods which Environment and Climate Change Canada has issued rainfall, wind or wave warning for the work area.
- An Erosion and Sediment Control Plan will be developed for the site that minimizes risk of sedimentation to the marine environment.
- Ensure that all in-water activities, or associated in-water structures, do not interfere with fish passage.
- Wash, refuel and service machinery and store fuel and other materials for the machinery in such a way as to prevent any deleterious substances from entering the water.
- Construction material and debris are not to become waterborne. Do not dispose of any materials or waste into marine environment.
- All equipment to be used in or over the marine environment is to be free from leaks or coating of hydrocarbon-based fluids and/or lubricants harmful to the environment. Hoses and tanks are to be inspected on a regular basis to prevent fractures and breaks.
- On site, crews must have emergency spill clean-up equipment adequate for the activity involved, and it must be on site. Spill equipment will include, as a minimum, at least one 250 L (i.e., 55 gallon) overpack spill kit containing items to prevent a spill from spreading; absorbent booms, pillows, and mats; rubber gloves; and plastic disposal bags. All spills or leaks must be contained, cleaned up, and reported to the 24-Hour Environmental Emergencies Report System (1-800-563-9089).
- Ensure that waste is not left at the work site. All construction waste material will be disposed of in a provincially approved manner.
- Workers in contact with hazardous materials must be provided with and use appropriate personal protective equipment.
- Proper safety procedures must be followed throughout the duration of the project as per applicable municipal, provincial, and federal regulations.
- Dispose of and stabilize all excavated material above the ordinary high water mark or top of bank of nearby waterbodies and ensure sediment re-entry is prevented.
- Replace/restore any temporarily disturbed habitat features and remediate any areas impacted by the works, undertakings or activity.
- Sediment controls will be visually monitored throughout the life of the project, and repaired immediately if necessary.
- Any debris or waste material will be disposed of in a provincially approved manner.
- Dust control should be provided for construction activities and open soil areas, primarily by using fresh water.
- Work is to be carried out during hours agreed upon with the Departmental Representative to mitigate any disturbance to harbour users and residents.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 3 | Notice of Determination | - | September 23, 2025 |
| 2 | End of Public Comment Period | - | October 25, 2024 |
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | September 25, 2024 |
Contacts
Fisheries and Oceans CanadaPaul Curran, Regional Engineer
John Cabot Building
St John's
10 Barters Hill
St. John's, Newfoundland and Labrador A1C 5X1
Telephone: 709-772-6660
Email: Paul.Curran@dfo-mpo.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- The Torbay SCH is a located on the eastern side of Newfoundland's Avalon Peninsula. (Newfoundland and Labrador)
-
Nature of Activity
- Ports and Harbours
-
Assessment Status
Completed -
Start Date
2024-09-25 -
Proponent
Fisheries and Oceans Canada - Small Craft Harbours (DFO-SCH) -
Authorities
- Fisheries and Oceans Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
88935
Nearby assessments
...within 200 kilometres-
Shoreline Protection, Flatrock, NL
The DFO-SCH project site is located in Flatrock, Newfoundland. -
Material Lay-down Area
St. John's -
Robin Hood Bay Radar Communications Site
Sugar Loaf Road, Robin Hood Bay, St. John's, NL -
Perimeter Ditching and Site Drainage Improvements
East White Hills -
New Trail Exit Construction
St. John's, Newfoundland -
Portugal Cove Light and Fog Signal Replacement
Portugal Cove -
Sir Humphrey Gilbert Building Radar Communications Site
Sir Humphrey Gilbert Building -
Steel Sheet Pile Wall Repairs St. John's Dockyard Limited
St. John's Harbour -
Wharf Replacement Pier 20 West and Pier 21
Pier 20/21 -
Pier 23 Upgrade – St. John's Harbour Terminal
Pier 23 - St. John's Harbour Terminal -
Proposal Removal and Relocation of Sediment within the Navigation Channel (St. John's Harbour)
Navigation Channel -
Proposed Removal and Relocation of Sediment at Piers 10 and 11 (St. John's Harbour)
Piers 10 and 11 (St. John's Harbour) -
Canadian Coast Guard Demolition of Administration Building, Southside Road, St. John's, NL
Southside Road, St. John's, NL -
Sediment Removal Under Syncrolift 2023
St. John's Dockyard Limited (NEWDOCK) -
Phase 1 of the Riverhead Wastewater Treatment Facility: Secondary Treatment Expansion Project
St. John's -
Wharf Reconstruction, St. Phillip's, Newfoundland
St. Phillip's -
Government of Canada Building Construction in St. John's, NL
80 Kelsey Drive, St. John's, Newfoundland. -
St. John's Small Concrete Dam Removal Project
St. John's -
Interior & Exterior Upgrades to Facility
Bell Island -
St. John's AAFC Research and Development Centre Waterline Upgrade Project
St. John's -
St. John's Building Retrofit Project
St. John's -
Completion of Route 3
Mount Pearl -
Installation of Septic Field
Cape Spear National Historic Site -
Main Electrical Feed Replacement
Cape Spear National Historic Site -
Breakwater Construction at Petty Harbour SCH, NL
Petty Harbour SCH is located in the community of Petty Harbour, Newfoundland. Located in the Avalon Peninsula, east of St. John’s, NL. -
Long Pond Development Project
Conception Bay South -
Harbour Redevelopment at Ship Cove SCH, NL
Ship Cove SCH is located in Port de Grave, Newfoundland. Port de Grave is located along the shore of Conception Bay, in the Avalon Peninsula. -
Sanitary and Storm Sewer Outfall Relocation
Harbour Grace -
Wharf Reconstruction, Harbour Grace, Newfoundland
Harbour Grace -
Wharf Reconstruction and Breakwater Extension, Ochre Pit Cove, NL
Ochre Pit Cove, Newfoundland -
Marginal Wharf Reconstruction, Port de Grave, Newfoundland
Port de Grave -
Wharf Reconstruction, Carbonear, Newfoundland
Carbonear -
DFO-SCH Shoreline Restoration / Armourstone Installation, Harbour Grace, NL
Harbour Grace -
Chapel's Cove Breakwater Mitigation Project
Town of Harbour Main - Chapel's Cove-Lakeview -
Warehouse Water and Sewer Servicing at Tilton Barrens, NL
The Tilton Barrens is a DFO property located at 899 Conception Bay Highway, Tilton, Newfoundland (NL). -
Repair, regrade and resurfacing parking lot - Bay Roberts Detachment
Bay Roberts -
Holyrood District Office & Detachment Re-grading and Re-surface of Parking Lot
36-40 Salmonier Line -
Main Beach Armour Stone
Old Perlican -
Bay de Verde SCH Southern Breakwater Extension
The Bay de Verde SCH is an incorporated town in Conception Bay on the northern tip of the Bay de Verde Peninsula of Newfoundland and Labrador. -
Wharf Construction, Bay de Verde, Newfoundland
Bay de Verde -
Cambrai Rifle Range Repair – Canadian Forces Station St. John's
Canadian Forces Station St. John’s -
Wharf Reconstruction, Old Perlican, NL
The DFO-SCH project site is located in Old Perlican, Newfoundland. -
DFO-SCH Finger Pier Extension, Old Perlican, NL
Old Perlican -
Wharf Reconstruction, Winterton, Newfoundland
Winterton -
Floating Dock construction, Whiteway, NL
DFO SCH Site in Whiteway, NL (DFRP # 00158) -
Wharf Reconstruction - Gooseberry Cove, Newfoundland
Gooseberry Cove -
Marginal Wharf Construction, Little Heart's Ease, NL
Little Heart's Ease, Newfoundland -
DFO-SCH New Marginal Wharf and Floating Docks, Hickman's Harbour, NL
Hickmans Harbour -
Newman Sound Day Use Area, HV cable replacement
Terra Nova National Park of Canada -
Finger Pier Reconstruction, Arnold's Cove, NL
Arnold's Cove -
Boat Launch Reconstruction, Arnold's Cove, NL
The DFO-SCH project site is located in Arnold's Cove, Newfoundland. -
Floating Dock Installation, Arnold's Cove, NL
Arnold's Cove, Newfoundland -
North East Arm Camp Hazardous Material Removal and Demolition
The Northeast Arm River is a scheduled salmon river that supports a recreational salmon fishery. The proposed project location is in the North East Arm Camp, accessible via Highway 100 in Dunville, Newfoundland. -
Utility pole installation along the Bell Aliant fibre optic line in Terra Nova National Park
Terra Nova National Park -
Wharf Construction, Riverhead, NL
Riverhead, Newfoundland -
Cooper Cove Marine Terminal Expansion Project
Placentia Bay -
Wharf Reconstruction, Jerseyside, Newfoundland
Jerseyside -
Argentia Inspection Station - Roof Replacement
Argentia -
Breakwater Construction, Summerville, N.L.
Summerville, NL -
Wharf Reconstruction, Bonavista, NL
The DFO-SCH project site is located in Bonavista, Newfoundland. -
Cape Race Building Demolition
Cape Race -
Wharf Repairs, Portugal Cove South, NL
The DFO-SCH project site is located in Portugal Cove South, Newfoundland. -
Boat Launch Construction, Trepassey, NL
Trepassey, Newfoundland -
Demolition of Cape Bonavista Loran A Site, Bonavista, Newfoundland and Labrador
The Cape Bonavista Loran A site was a long-range radio navigation station located approximately five kilometers north of Bonavista, Newfoundland and Labrador (NL) between Cape Shore Road to the West and the shoreline of Cape Bonavista to the East -
Bristy Cove Bridge Rehab
The project is located at Bristy Cove River in the community of Trepassey along the road to Cape Race. -
Cape Bonavista Tower Replacement
The DFO-RPSS project site is located in Cape Bonavista, Newfoundland. -
Dredging Branch, NL
Branch -
Capital work at the Port Blandford Marina
Town of Port Blandford -
Construction of a mountain bike skills trail in Newman Sound, Terra Nova National Park
Terra Nova National Park of Canada -
Water and Sewer Utility Systems Recapitalization - Phase 2
Terra Nova National Park -
Entrance Washrooms Sanitary Rehabilitations
Terra Nova National Park -
Routine Vegetation Maintenance at Terra Nova Golf Resort and Community
Terra Nova National Park -
Vegetation Maintenance along the Bell Aliant Fibre Optic Line
Terra Nova National Park -
Water Withdrawal from Northwest River, Terra Nova National Park, for Golf Course Irrigation
Terra Nova National Park -
Shoreline Protection, St. Bride's, NL
The DFO-SCH project site is located in St. Bride's, Newfoundland. -
Wharf Reconstruction at St. Bride's SCH, Newfoundland and Labrador
The St. Bride's SCH is located within St. Bride's, on the southwestern shore of the Avalon Peninsula, NL. -
Water and Sewer Utilities System Recapitalisation - Phase 3
Terra Nova National Park -
Fishway Refurbishment, Lower Terra Nova River, NL
The DFO-RPSS project site is located in Terra Nova, Newfoundland. -
Helicopter Pad Replacement, Puffin Island, NL
The DFO-RPSS project site is located on Puffin Island, Bonavista Bay, Newfoundland. -
Puffin Island Fuel Tank Replacement
Puffin Island, Bonavista Bay, NL -
Lauchway Reconstruction, St. Bernard's, NL
The DFO-SCH project site is located in St. Bernard's, Newfoundland. -
Greenspond SCH Wharf Reconstruction
The Greenspond SCH is located on the island of Greenspond, within Bonavista North, in Bonavista Bay, on the northeast coast of the Island of Newfoundland. -
Fishway Refurbishment, Middle Brook, NL
Middle Brook, Newfoundland -
Floating Dock Reconstruction, Wesleyville (Brookfield), NL
Wesleyville -
Interior & Exterior Upgrades to Facility
New Wes Valley -
Comfort Cove Building Demolition
Comfort Cove -
Aid to Navigation Tower Refurbishments - Coast of Newfoundland
Coast -
Installation of an Outfall Pipeline, Mortier Bay, NL
Outfall Pipeline, Mortier Bay, NL -
Marbase Lumpfish Hatchery - Saltwater Intake and Discharge Pipelines, Marystown, NL
Marystown -
Marystown RCMP Detachment Replacement Project
Marystown -
Gander Very High Frequency Omni-directional Range (VOR) Replacement
Gander -
Repair Cross Loop Access Road - Canadian Forces Station (CFS) Leitrim, Gander
Canadian Forces Station Leitrim, Gander -
Wharf Demolition, Burin, NL
The DFO-RPSS project site is located in Burin, Newfoundland. -
Burin Search and Rescue Wharf Construction
Canadian Coast Guard Search and Rescue Station, Burin -
Relocate Sewage Lift Station at Hangar 1, Canadian Forces Base 9 Wing Gander, Newfoundland and Labrador
Hangar 1, Canadian Forces Base 9 Wing Gander -
Lauchway Reconstruction, Burin, NL
The DFO-SCH project site is located in Burin, Newfoundland. -
Accommodation for Wing Headquarters - 9 Wing Gander
9 Wing Gander -
Construct New Military Family Resource Centre - Canadian Forces Base (CFB) Gander
Canadian Forces Base (CFB) Gander -
Explosives Storage Area Fence Repairs at 9 Wing Gander, Canadian Forces Base Gander, Newfoundland and Labrador
9 Wing Gander -
Brush Cutting and Fence Line Repairs - Canadian Forces Base (CFB) Gander
Canadian Forces Base (CFB) Gander -
Upgrade Building B160 for Occupancy - 9 Wing Gander
9 Wing Gander