Royal Avenue Reconstruction - Canadian Forces Base Shilo

The Department of National Defence (DND) has proposed a project. In general, the work includes:

  1. Removal of existing roadway, sidewalks, storm sewer and watermain along Royal Avenue.
  2. New storm sewers and catch basins along Royal Avenue.
  3. New watermain and hydrant along Royal Avenue.
  4. New sidewalks, new paving.

Latest update

July 22, 2023 – The public comment period on the project is closed. The Department of National Defence is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
1 Public Comment Period on Intent to Make a Determination - July 12, 2023

Contacts

Robert Riesz
Department of National Defence
Robert Riesz, Base Engineering Officer
PO Box 5000, Station Main
Shilo, Manitoba R0K 2A0
Email: Robert.Riesz@forces.gc.ca


  • Location

    • Canadian Forces Base Shilo (Manitoba)
  • Nature of Activity

    • Highways and Roads
  • Assessment Status

    In progress
  • Start Date

    2023-07-12
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    85757
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 