Ebb and Flow First Nation - Road and Drainage Upgrades

  • Upgrade 6 existing community roads
  • Construct new drainage ditching and swales along roads and re-grade existing ditching and swales
  • Replace and install new culverts on upgraded road sections.
  • Reconstruct driveaway approaches along upgrade road sections.
  • Existing road surface will be re-graded and re-constructed with compacted subgrade and granular road base from local borrow pits.
  • 75,000 sq.m.

Latest update

August 19, 2024 – Indigenous Services Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination - August 19, 2024
1 Notice of Intent to Make a Determination - Start of Public Comment Period - June 24, 2024

Contacts

Indigenous Services Canada (ISC)
Shelly Johnson, Senior Environmental Specialist
200 - 365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-227-3891
Email: shelly.johnson@sac-isc.gc.ca


  • Location

    • Ebb and Flow First Nation (Manitoba)
  • Nature of Activity

    • Highways and Roads
  • Assessment Status

    Completed
  • Start Date

    2024-06-24
  • Proponent

    Ebb and Flow First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    88664