Breakwater Reconstruction at Sandford Small Craft Harbour, Yarmouth County, NS

The Small Craft Harbours Branch of Fisheries and Oceans Canada proposes to undertake a breakwater reconstruction and expansion project at Sandford Harbour, located in the community of Sandford, Yarmouth County, Nova Scotia. The breakwater currently contains remnants of a failed crib wharf which will be removed to the corestone limits of the new breakwater structure and disposed of in a provincially-approved manner. Once the wharf removal is complete, new and reinstated corestone will be built up on either side of the wharf remnants. Two layers of filterstone will be placed on top of the corestone and overlain with two layers of armourstone. The work could result in a total footprint change of up to 700 m2. The crest elevation will be approximately +7.5 m above chart datum with a width of 4.5 m, transitioning into an elevation of +8.3 m above chart datum with a crest width of 3.7 m at the toe of the breakwater. Side slopes will be constructed at a general 2:1 ratio, with the inner side of the toe increasing the slope slightly to accommodate for the increased elevation. Existing armourstone from the current structure will be salvaged for reuse where possible.


Latest update

Notice of Determination

November 15, 2023 – The Federal Authorities have issued their Notice of Determination after evaluation of the breakwater reconstruction at the Sandford DFO-SCH, and have determined that the project is not likely to cause significant adverse environmental effects and can therefore proceed.

 

This determination was based on a consideration of the following factors:

  • Impacts on rights of Indigenous peoples;
  • Community and Indigenous knowledge;
  • Comments received from the public; and
  • Technically and economically feasible mitigation measures.

 

Mitigation measures taken into account for this determination are:

  • To minimize the possibility of fish habitat contamination and the spread of aquatic invasive (alien) species, all construction equipment which will be immersed into the water or has the possibility of coming into contact with such water during the course of the work, must be cleaned and washed to ensure that they are free of marine growth and alien species.
  • Weather conditions are to be assessed on a daily basis to determine the risk of extreme weather in the project areas. Avoid work during periods which Environment and Climate Change Canada has issued rainfall, wind or wave warning for the work area.
  • An Erosion and Sediment Control Plan will be developed for the site that minimizes risk of sedimentation to the marine environment.
  • Ensure that all in-water activities, or associated in-water structures, do not interfere with fish passage.
  • Wash, refuel and service machinery and store fuel and other materials for the machinery in such a way as to prevent any deleterious substances from entering the water.
  • Construction material and debris are not to become waterborne. Do not dispose of any materials or waste into marine environment.
  • All equipment to be used in or over the marine environment is to be free from leaks or coating of hydrocarbon-based fluids and/or lubricants harmful to the environment. Hoses and tanks are to be inspected on a regular basis to prevent fractures and breaks.
  • On site, crews must have emergency spill clean-up equipment adequate for the activity involved, and it must be on site. Spill equipment will include, as a minimum, at least one 250 L (i.e., 55 gallon) overpack spill kit containing items to prevent a spill from spreading; absorbent booms, pillows, and mats; rubber gloves; and plastic disposal bags. All spills or leaks must be contained, cleaned up, and reported to the 24-Hour Environmental Emergencies Report System (1-800-565-1633).
  • Minimize disturbance to all birds and wildlife on-site and in adjacent areas during the entire course of the work.
  • During nighttime work (if any), lights are to be shielded or pointed downwards. They are to be positioned in the opposite direction of any nearby bird nesting habitat.
  • Ensure that food scraps and garbage are not left at the work site. All construction waste material will be disposed of in a provincially approved manner.
  • No one shall disturb, move, or destroy migratory bird nests.
  • Should nests or chicks of migratory birds or raptors be encountered during work, immediately stop work in that area and notify Departmental Representative for directives to be followed. Should a nest site be discovered:
    • The nest site and neighbouring vegetation will not be disturbed until nesting is completed.
    • Work undertaken immediately adjacent to such areas will be minimized until nesting is completed.
  • If an archaeological and/or historically significant item is discovered during the work activities, work in the area will be stopped immediately and the PSPC Project Manager will be contacted as well as the provincial Archaeological Services unit: Nova Scotia Department of Communities, Culture and Heritage, Special Places Program - telephone: (902) 424-6475. Work will only resume at the direction of the provincial Archaeologist.
  • Workers in contact with hazardous materials must be provided with and use appropriate personal protective equipment.
  • Proper safety procedures must be followed throughout the duration of the project as per applicable municipal, provincial, and federal regulations.
  • All equipment used for the works must be in good working condition.
  • No construction or infill material may be obtained from any coastal feature, namely a beach, dune, or coastal wetland.
  • Wherever possible, machinery will operate from a barge or from land or infrastructure above the high water mark in a manner that minimizes disturbance.
  • Dispose of and stabilize all excavated material above the ordinary high water mark or top of bank of nearby waterbodies and ensure sediment re-entry is prevented.
  • Control runoff of water containing suspended material or other harmful substances in accordance with requirements of all federal, provincial and municipal authorities having jurisdiction.
  • Coastal habitats outside the project area must not be accessed by heavy equipment nor used as staging areas.
  • Operate machinery in a manner that minimizes disturbance to the watercourse bed and banks.
  • Replace/restore any temporarily disturbed habitat features and remediate any areas impacted by the works, undertakings or activity.
  • Sediment controls will be visually monitored throughout the life of the project, and repaired immediately if necessary.
  • Any debris or waste material will be disposed of in a provincially approved manner.
  • Eliminate free board spillage when excavating, loading and hauling material. Do not dump petroleum products or any other deleterious substances on ground.
  • Dust control should be provided for construction activities and open soil areas, primarily by using fresh water. Waste oil or other petroleum products shall not be used for dust control under any circumstances. Where and when applicable (e.g., during a dry summer), other agents such as calcium chloride may be used for dust suppression. The use of calcium chloride will be in accordance with the guidelines outlined in Environment Canada’s Best Practices for the Use and Storage of Chloride-Based Dust Suppressants, referring to how, when and quantity to apply.
  • All dust control agents shall be stored in areas away from water bodies and contained, to prevent entry into water bodies.
  • Work is to be carried out during hours agreed upon with the Departmental Representative to mitigate any disturbance to harbour users and residents.
  • A safety zone for cetaceans and/or species listed under Schedule 1 of the Species at Risk Act (e.g. North Atlantic Right Whale, White Sharks or Atlantic Salmon) must be established at the work site. The safety zone shall consist of a circle with a radius of at least 500 meters as measured from the center of the work site.
  • If cetaceans and/or species listed under Schedule 1 of the Species at Risk Act are observed within the safety zone while in-water activities are underway, all in-water activities must cease until the animals leave the safety zone and are not observed within the safety zone for a minimum period of 30 minutes.
  • Work may start or restart if cetaceans and/or species listed under Schedule 1 of the Species at Risk Act are not observed within the safety zone within the 30-minute period.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination - November 15, 2023
1 End of Public Comment Period - August 16, 2022

Contacts

Fisheries and Oceans Canada - Small Craft Harbours, Maritime and Gulf Region
Chyann Kirby, Regional Environmental Advisor
Gulf Fisheries Centre, 343 University Avenue
Moncton, New Brunswick E1C 9B6
Telephone: 506-866-5164
Email: chyann.kirby@dfo-mpo.gc.ca


  • Location

    • Sandford SCH is located in the community of Sandford, Yarmouth County, Nova Scotia, and can be accessed from Ross Durkee Road before egressing onto the Sandford Wharf Road. (Nova Scotia)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    Completed
  • Start Date

    2022-07-11
  • Proponent

    Fisheries and Oceans Canada - Small Craft Harbours (DFO-SCH)
  • Authorities

    • Fisheries and Oceans Canada
    • Transport Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    83784
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: