The Proposed Project
The Project includes the expansion of an existing lagoon, as it is currently too small for its design population. The new lagoon is expected to have a 220-day storage capacity and a 20-year design life. Treatment cells will require an expansion of 19,100m2 in surface area and storage cells will require an expansion of 77,000m3 in volume. Lagoon design was determined in accordance to the current Indigenous Services Canada and Water Security Agency sizing requirements. Compacted clay liners will be used to keep lagoon seepage to a minimum and protect surrounding land and groundwater. Berms between lagoon cells will be constructed with a top width of at least 10 feet to accommodate maintenance vehicle access.
Project involves expanding the existing wastewater lagoon by construction new cells. The existing force main will also be extended.
Lagoon Construction
- strip and stockpile topsoil.
- excavate and stockpile medium plastic clay
- construct berms.
- excavate subgrade soil.
- form positive seal between berm fill and undisturbed soil
- install clay liner
- replace topsoil and seed areas where needed
Minimal construction waste will be generated, which will be deposited in a licensed nearby facility. Desludging activities will be carried out and sludge will be dried on site. No hazardous waste is expected to be generated by this project. Clearing is planned to occur in the winter to lessen potential impacts to nesting birds.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination for Mosquito First Nation Lagoon Upgrades | - | February 8, 2022 |
1 | Public Comment Period on Intent to Make a Determination | - | December 22, 2021 |
Contacts
ISC-SKENVIndigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
-
Location
- Mosquito First Nation (Saskatchewan)
-
Nature of Activity
- Water Management
- Waste Management
-
Assessment Status
Completed -
Start Date
2022-01-06 -
Proponent
Mosquito First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
83264
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Mosquito Grizzly Bear's Head Lean Man First Nation - Core Area Subdivision
Mosquito Grizzly Bear's Head Lean Man First Nation -
Sweetgrass New School
Sweetgrass IR 113 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Sweetgrass First Nation Wastewater System Upgrades
Sweetgrass First Nation -
Little Pine First Nation Lagoon Upgrade and Bridge over Battle River
Little Pine IR No. 116 -
Great Sandhills Railway Switching Operation at North West Terminal Project
1 kilometre east of Unity -
Great Sandhills Railway Switching Operation at North West Terminal Project - Revised Design
1 kilometre east of Unity, Saskatchewan -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Kerrobert -
Thunderchild First Nation Lagoon Upgrade
Thunderchild IR115B -
Thunderchild First Nation - Solid Waste Transfer Station
Thunderchild IR115B & 115C -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
Thunderchild First Nation - Turtle Lake Site 115C WTP Process Waste Pond
Thunderchild IR 115C -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
Apron III infill
Saskatoon International Airport YXE -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Nutrien Aviation Hangar Expansion
STARS Saskatoon Base -
Kahkewistahaw First Nation - Mamawi Business Center
Kahkewistahaw No. 72A -
Saskatchewan Indian Institute of Technologies Hangar Expansion
Saskatchewan Indian Institute of Technologies -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
Thunderchild First Nation Powwow Arbor
THUNDERCHILD FIRST NATION 115B -
Thunderchild First Nation Water Treatment Plant and Well Upgrades
THUNDERCHILD FIRST NATION 115B -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
Thunderchild Wellness Centre
Thunderchild Wellness Centre -
Regional Psychiatric Centre
Regional Psychiatric Centre -
Witchekan Lake First Nation Solid Waste Transfer Station
Witchekan Lake First Nation -
Saulteaux IR159 Timber Harvest Plan 2020-21
Saulteaux IR 159EE -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Saulteaux IR159 Timber Harvest Plan 2021-22
Saulteaux IR 159EE -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Big River First Nation Reserve Drainage Re-Establishment
Big River First Nation -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Dakota Springs Spa
Whitecap IR #94 -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Whitecap Dakota Nation Virtual Health Hub
Whitecap Dakota First Nation No 94 -
Mistawasis Nehiyawak Lagoon Upgrades
Mistawasis Nêhiyawak -
New Fibre Installation, Upgrade (Single) Tower
Moonlight bay -
Thunderchild First Nation - Turtle Lake Site 115C Sewage Lagoon Operations
Thunderchild First Nation -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
Fishing Lake First Nation Sewage Pumping Station Upgrades
Fishing Lake First Nation -
Cree Nation Treatment Haven Replacement
Ahtakakoop First Nation -
Pelican Lake Community Harvest Program Phase 2022-2024
Chitek Lake IR 191 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
Magazine Area Recapitalization Canadian Forces Ammunition Depot (CFAD) - 17 Wing Detachment Dundurn
Canadian Forces Ammunition Depot Dundurn,17 Wing Detachment Dundurn -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Pelican Lake First Nation - Quonset Addition
Chitek Lake IR 191 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Beardy's and Okemasis Cree Nation Water Treatment Plant Upgrades Project
Beardy's and Okemasis Cree Nation -
Pelican Lake First Nation 191 A, B, C, D Gasification Project
Pelican Lake First Nation 191 A, B, C, D -
Pelican Lake Farms - farm site development
Pelican Lake IR 191-B -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Pelican Lake Bioenergy Project
Pelican Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Beardy's & Okemasis Cree Nation Stage 4 Subdivision
Beardy's & Okemasis Cree Nation -
Pelican Lake Timber Harvesting Plan 2021-22
Chitek Lake IR 191 & 191A -
Pelican Lake Timber Harvesting Plan
Chitek Lake IR 191 -
Pelican Lake North Sewage Lagoon Expansion and Upgrades
Chitek Lake IR 191 -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
Mistahi Sipiy Child and Family Service and Big River First Nation Prevention Building
Big River First Nation -
Willow Cree Healing Lodge - Construction of Ready to Move (RTM) Buildings
Willow Cree Healing Lodge -
Big River First Nation Arena Build Project
Big River IR 118 -
Batoche Drainage Improvement
Grasslands National Park -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site -
Remediation of One Arrow First Nation River Lot 62
One Arrow IR 95 -
Ahtahkakoop South Subdivision Phase 1
Ahtakakoop Cree Nation -
Lac Eauclaire Timber Harvest Program
Pelican Lake IR 191-C -
Beaver dam and lodge removal
Prince Albert National Park -
SaskPower Pole Mount Transformer Replacement for Hawood
Prince Albert National Park -
Building Foundation Removal and Site Restoration in Lost Farm Area at 3CDSB Wainwright
The Range Training Area (RTA) at Detachment Wainwright -
Onion Lake Cree Nation Aquatic Centre Project
Onion Lake Cree Nation Aquatic Centre Project -
On Hold - Aggregate Business Development Plan - Phase 2, Sturgeon Lake First Nation I.R. 101
Sturgeon Lake IR 101 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 1 -
Flying Dust Commercial Project
Meadow Lake -
Kapasiwin Bungalows Installation of Deep Water and Sewer Infrastructure
Prince Albert National Park -
Zagime Anishinabëk RV Trailer Park
Sakimay IR 74 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 2 -
Electrical Power Upgrade for Building 650 (B650) at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Railhead at Garrison Wainwright
Garrison Wainwright (Denwood) -
New Power Line Installation
CFB Suffield, Medicine Hat -
Reconfigure Power Distribution at the Exercise Control Site
CFB Suffield, Medicine Hat -
Upgrades to Roads within Administrative Area- Garrison Wainwright
Garrison Wainwright -
Blanket Permit - SaskEnergy - Gasification of Sturgeon Lake Indian Reserve No. 101
Sturgeon Lake Indian Reserve No. 101 -
Skate Park Design-Build Project - Garrison Wainwright
Garrison Wainwright -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 2) -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 633) -
Demolish Pre-Wash Facility - Garrison Wainwright
Garrison Wainwright -
Front Gate Water Loop - Garrison Wainwright
Garrison Wainwright in Denwood -
Upgrade Main Petroleum Oils and Lubricants (POL) Facility at Garrison Wainwright
Garrison Wainwright in Denwood -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Bulk parking lot) -
Construct Hazardous Waste Storage Facility - Garrison Wainwright
Garrison Wainwright -
Demolition of Tent City, Building 313 and Water Point - Garrison Wainwright
Garrison Wainwright -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 2) -
RW-4851 Authorization to Construct and Operate a Right of Way for a gas pipeline
Frog Lake First Nation -
Upgrade Water and Sewer Utilities to Building AW22 at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Range 1 at Garrison Wainwright
Garrison Wainwright in Denwood -
Provide Power to Troop Shelters at Garrison Wainwright
Garrison Wainwright (Denwood) -
Flying Dust - New Water Treatment Plant
Flying Dust IR 105 -
Install Cattle Watering Line in the Range and Training Area - Garrison Wainwright
Garrison Wainwright -
Remedial activities at a site impacted by Aqueous Film Forming Foam (AFFF) - Garrison Wainwright
Garrison Wainwright -
Upgrades to Range 8 - Garrison Wainwright
Garrison Wainwright -
Construct Sniper Range at Garrison Wainwright
Garrison Wainwright (Denwood) -
Sturgeon Lake First Nation - East Lagoon Expansion
Sturgeon Lake IR 101 -
Wahpeton Dakota Nation Sewage Lagoon Expansion
WAHPATON INDIAN RESERVE NO. 94A -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
EAGLES LAKE I.R. 165C -
Sturgeon Lake First Nation Subdivision
Sturgeon Lake IR 101A -
Peter Ballantyne Child and Family Services Facility
Kistapinin IR 211 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 3 -
Sturgeon River Pedestrian Bridge
Sturgeon Lake Indian Reservation No.101 -
Flying Dust First Nation Regional Landfill
Flying Dust IR 105 -
Makwa Lake Resort Development
Makwa Lake Indian Reserve No. 129B -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 1) -
SaskPower HR-01033 - RPD-511 PQ Rural Rebuild (Makwa Rebuild)
Makwa First Nation -
Peter Ballantyne Child and Family Services Inc. Central Office Extension
Chief Joseph Custer Reserve -
Sturgeon Lake First Nation - Renovation for gas bar and convenience store
Sturgeon Lake First Nation - Prince Albert Strip Mall -
Potential Regional Assessment of a Western Energy Corridor from Alberta to Manitoba
Prince Albert -
Potential Regional Assessment of a Western Energy Corridor
near Prince Albert -
Install New Trailer Complex at P12 at Garrison Wainwright
Garrison Wainwright (near Denwood) -
Fenceline Replacement - Prince Albert Training Area, Saskatchewan
DND Prince Albert Training Area -
Hunters Lake Trail Rehabilitation
Prince Albert National Park -
Biocontrol of Yellow Toadflax using Rhinusa pilosa, in Prince Albert National Park
Prince Albert National Park -
Lake Diefenbaker Irrigation Expansion Projects
Lake Diefenbaker -
Montreal Lake IR 106B Gasification
Montreal Lake IR 106B -
Montreal Lake Cree Nation Little Red River Water Treatment Plant Upgrade Project
Montreal Lake Cree Nation -
SaskPower Ground Mount Transformer Installation Red Deer Campground
Prince Albert National Park of Canada -
SaskPower Transformer Salvage
Prince Albert National Park -
Battle River Pumphouse Replacement - Garrison Wainwright
Garrison Wainwright -
Montreal Lake Cree Nation & Little Red River Solid Waste Transfer Station & Decommissioning
Montreal Lake IR 106B -
SaskPower Poles Replacement in Prince Albert National Park near south west boundary.
Prince Albert National Park -
SaskPower Ground Grid Replacement near MacKenzie Creek
Prince Albert National Park -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161A -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 750) -
Tway National Wildlife Area Water Control Structure Re-naturalization Project.
Tway National Wildlife Area -
SaskPower Pole Replacement near Halkett (Sandy) Lake
Prince Albert National Park -
Stabilize Temporary Bridge Abutments - Garrison Wainwright
Garrison Wainwright -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 3) -
Demolish and Upgrade Vertical Village - Garrison Wainwright
Garrison Wainwright -
SaskPower Pole Replacement in Prince Albert National Park - east of Sandy Lake
Prince Albert National Park -
Ministikwan Subdivision Development
Ministikwan IR 161 -
Construction of a Royal Canadian Mounted Police Detachment in Vermilion, Alberta
Vermilion -
Hardisty Rail Terminal Project
10 km southeast of Hardisty -
Potential Regional Assessment of a Western Energy Corridor
near Vermilion -
Ministikwan Lake Cree Nation - Solid Waste Transfer Station
Ministikwan IR161 -
Muskoday First Nation - Construct Cultural Centre
Muskoday First Nation - Construct Cultural Centre