Paving project at Garrison Wainwright

This project involves applying asphalt to existing parking areas at Garrison Wainwright. The locations and current conditions of the parking lots are: Building 633 (asphalt), Building 750 (dirt/gravel) and Bulk parking area (gravel). Construction is planned for summer 2021. Project activities include:
· Removal and storage of topsoil as required.
· Minor grading as required in gravel areas to level low spots.
· Removal and disposal of old asphalt as required.
· Application of asphalt.
· Landscaping, as required.


Latest update

June 11, 2021— The Department of National Defence issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

.

Participate

Contacts

Project Manager, Real Property Operations Unit (West) Detachment Wainwright
Department of National Defence
Caroline Paquin, Project Manager, Real Property Operations Unit (West) Detachment Wainwright
Real Property Operations Unit (West) Detachment Wainwright
Denwood, Alberta T0B 1B0
Telephone: 780-842-1363 ext. 1361
Email: caroline.paquin@forces.gc.ca


  • Location

    • Garrison Wainwright in Denwood (Building 633) (Alberta)
    • Garrison Wainwright in Denwood (Building 750) (Alberta)
    • Garrison Wainwright in Denwood (Bulk parking lot) (Alberta)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2021-03-15
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    81445
Disclaimer