Magino Gold Project

Comment Search Mobile

Comment Search

Skip to filters

4 results

Attachment Proposed project changes due to addition of 22-megawatt on-site liquefied natural gas-fired electrical power generation facility

  • Magino Gold Project
  • Author: Red Sky Metis Independent Nation
  • Reference Number: 63
  • Submitted: 2023-07-11 - 12:23 PM
  • Project Phase: N/A
  • Participation Notice: N/A
  • Red Sky Métis Independent Nation (RSMIN) thanks you for the opportunity to comment on the above noted project. After reviewing the RSMIN community data and the details of the project, at this time the RSMIN community does have some concerns regarding the current land use for the proposed project activities. The location of the project area falls within an area that is extensively used for traditional purposes.  The following comments and concerns need to be addressed: The proposed truck route needs to be clarified for our community to understand the environmental impacts. How did the proponent decide the route? Is the liquefied natural gas coming from Ontario or Quebec? What company is trucking the LNF?  
  • Attachment Included
  • 406 Victoria Avenue East, Thunder Bay, Ontario, Canada P7C 1A5 Phone: (807) 623-4635 Email: Consultation@RSMIN.ca Website: www.rsmin.ca July 11, 2023 Kimberly Browning Impact Assessment Agency of Canada Kimberley.Browning@iaac-aeic.gc.ca Dear Kimberly Browning, RE: Magino Gold Project –Proposed project changes due to addition of 22-megawatt on-site liquefied natural gas-fired (LNF) electrical power generation facility Red Sky Métis Independent Nation (RSMIN) thanks you for the opportunity to comment on the above noted project. After reviewing the RSMIN community data and the details of the project, at this time the RSMIN community does have some concerns regarding the current land use for the proposed project activities. The location of the project area falls within an area that is extensively used for traditional purposes. The following comments need to be addressed: • The proposed truck route needs to be clarified for our community to ...

Report

Attachment RE: Magino Gold Project - Comments welcome by July 6, 2023 - Proposed project changes due to addition of 22-megawatt on-site liquefied natural gas-fired electrical power generation facility

  • Magino Gold Project
  • Author: Administrator on behalf of Missanabie Cree First Nation
  • Reference Number: 62
  • Submitted: 2023-07-06 - 2:32 PM
  • Project Phase: N/A
  • Participation Notice: Public Notice - Public comments invited on proposed changes to the project
  • Please see the attached submission. 
  • Attachment Included
  • RE: Missanabie Cree First Nation COMMENTS to the Impact Assessment Agency of Canada Supplemental Impact Assessment Report - Magino Gold Project COMMENT #1 MCFN Cumulative Effects Concerns for ECA Air/Noise sent to MECP – Shareen Han _ Senior Program Support Coordinator, Permissions and Program Services Unit, October 19, 2022. Shareen Han – MECP response received November 8, 2022. MECP response – Each mine is reviewed individually, and states that neither proponent meets the requirements under the cumulative effects policy for air emissions on an individual basis. Each operation may be able to comply with Ontario’s air emissions standards (O.Reg. 419/05) on an individual application, but the policy that regulates cumulative effects cannot be pre-determined in an individual application framework. Cumulative effect considerations should require the Ministry to evaluate the assembled information from both proponents prior determining whether the proponent meets ...