STPFN Wastewater Treatment Plant Upgrade and Expansion Project
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The proposed project is to upgrade and expand the wastewater treatment facility for the St. Theresa Point First Nation (STPFN). STPFN is an Indigenous community located in the Island Lake region of Manitoba, approximately 460 kilometers northeast of Winnipeg. The community is accessible year-round by air and via winter road from February to March. The 2021 on-reserve population is 4,062 people (INAC, 2021). Wastewater is collected in the community through trucked and piped sewage services. There are two wastewater treatment plants (WWTPs) currently servicing the community: the North WWTP (UTM coordinates 15 U 378398 m E 5966032 m N and the South WWTP (UTM coordinates 15 U 377642 m E, 5963684 m N). Both WWTPs discharge the treated effluent to Island Lake on the east shore of the community.
Results from a previous feasibility study indicated that both WWTPs have substantial operational issues and are in a state of disrepair, requiring upgrading (Neegan Burnside, 2020). In addition, the sludge drying bed area, located approximately 5 km south of the South WWTP is not being operated as intended and sludge from both WWTPs has not been taken to the sludge drying bed in several years. Raw wastewater from holding tanks has also been periodically dumped into the sludge drying beds, which appear to be overflowing and partially covered with windblown litter from the adjacent community landfill. To address current deficiencies, operational challenges and accommodate the current wastewater flows and future community growth, the North WWTP will be decommissioned and the South WWTP will be upgraded and expanded with additional upgrades made to the wastewater collection system and the sludge drying beds. The upgraded South WWTP currently has an average design capacity of 1,480 m3/day. With the expansion, it will have the capacity to meet 20-year projected flows of an average 2,100 m3/day.
The STPFN wastewater treatment plant upgrade and expansion project (the Project) consists of the repair/upgrade and decommissioning of wastewater infrastructure in the community, including:
- Constructing a new lift station (North Lift Station) installed approximately 10 m north of the
North WWTP to service the north catchment area of STPFN and convey wastewater to the South
WWTP. - Installing a 250 mm diameter gravity sewer connecting the manhole of the North WWTP (MH
79) to the North Lift Station. - Decommissioning the existing Lift Station #4 and installing a new 200 mm diameter gravity sewer line (approximately 8 m in length) to convey wastewater flowing from the decommissioned lift station #4 to the North Lift Station.
- Installing a new 200 mm high density polyethylene (HDPE) forcemain (approximately 2.65 km in length) connecting the North Lift Station to existing gravity sewer at Manhole #8.
- Upgrading, repairing, and expanding the existing South WWTP, including construction of the
expanded superstructure, new truck dump pad and manhole, installation/repairs to process and
mechanical equipment, a new 300 mm gravity effluent overflow outfall discharging to rip rap
east of the superstructure on the shore of Island Lake, and a new 375 mm gravity sewer line
(approximately 60 m in length) to Manhole #4. - Upgrading the sludge drying beds by draining away the liquid and hauling it to the South WWTP,
allowing sludge to dry, pushing sludge into stockpiles, and re-grading the site to prevent accumulation of rain/snow. - Upgrading (widening) and re-surfacing the access road to the sludge drying beds to
accommodate truck turn around. - Decommissioning of the North WWTP.
During operation, the WWTP treatment process produces sludge (56 m3/day at 0.85% solids) and treated wastewater effluent (40 L/s). Sludge will be de-watered using de-watering trailers and approximately 1.73 m3 /day of de-watered sludge will be hauled to the sludge drying beds on a regular basis (approximately every 7 days). Dried sludge will be hauled to the neighboring community landfill site, on an as-needed basis, to be used as interim cover material. Treated wastewater effluent will be discharged to Island Lake on a continuous basis through the existing discharge/outfall structure. General office waste will be sent to the local community waste disposal ground. The effluent will be monitored continuously to confirm it meets the effluent discharge criteria as described in the Wastewater Systems Effluent Regulations (2017). Should a flood event occur, the South WWTP will discharge wastewater overflows to Island Lake via a 300 mm gravity effluent overflow outfall as an emergency measure. During decommissioning of the North WWTP, STPFN may choose to retain the existing WWTP building for a future use as a storage facility. Sewage and liquid wastes from the North WWTP will be hauled to the new truck haul wastewater receiving station while the sludge would be disposed of at the sludge drying beds following dewatering. During decommissioning of Lift Station #4, sewage and liquid wastes will be hauled to the new truck haul wastewater receiving station. The internal infrastructure (piping, valves, pumps, etc.) will be removed and disposed of at the landfill. The control panel will be salvaged and handed over to STPFN to use as parts for the other lift stations in the community.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination | - | April 19, 2023 |
1 | Comment Period on Intent to Make a Determination | - | September 2, 2021 |
Contacts
Indigenous Services CanadaShelly Johnson, Environmental Specialist
365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-984-0709
Email: shelly.johnson@canada.ca
-
Location
- St. Theresa Point First Nation (Manitoba)
- St. Theresa Point First Nation (Manitoba)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2021-09-02 -
Proponent
St. Theresa Point First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
82963
Nearby assessments
...within 200 kilometres-
St. Theresa Point First Nation - Old Bulk Fuels Decommissioning
St. Theresa Point First Nation -
St Theresa Point Northern Store Contamination Remediation
St Theresa Point Former Bulk Fuel Plant -
Theresa Point First Nation road re-construction
St Theresa Pt First Nation -
Wasagamack First Nation Leachate Management Upgrades (Engineered Wetlands) - 2021
Wasagamack First Nation -
Aboveground Fuel Storage Replacement in Island Lake, Manitoba
Island Lake -
God's Lake First Nation Lumber Compound Site Fencing
God's Lake First Nation -
Project 6 - All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation
-
God's Lake First Nation Water Treatment Plant (WTP) Upgrades
God's Lake First Nation -
God's Lake Soil Remediation Project
God's Lake First Nation -
God's Lake Soil Remediation Project
God's Lake First Nation -
God's Lake First Nation Water Treatment Plant (WTP) Upgrades
God's Lake First Nation -
Aboveground Fuel Storage Replacement in God's Lake Narrows, Manitoba
God's Lake Narrows -
Red Sucker Lake First Nation New Aerated Lagoon
Red Sucker Lake First Nation -
Red Sucker Lake First Nation New Landfill
Red Sucker Lake -
Red Sucker Lake New School and Servicing
Red Sucker Lake First Nation New School and Services -
Project 6 — All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation
-
Remediation of Former Band Tank Farm Site
Manto Sipi Cree Nation -
Project 6 - All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation
-
Bunibonibee Cree Nation - 48 Unit Subdivision
Bunibonibee Cree Nation -
Project 6 — All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation
East of Lake Winnipeg -
New Fibre Installation / Upgrade Multiple Towers
Muskrat Dam PoP -
Sandy Lake First Nation - Child and Family Services Building
Sandy Lake First Nation -
Sandy Lake Cultural Area
Sandy Lake -
Deer Lake First Nation Small Business Center Project
Deer Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Wapekeka (Angling Lake) PoP -
New Fibre Installation / Upgrade Multiple Towers
Big Trout Lake PoP -
Keewaywin First Nation New Landfill Construction and Old Landfill Decommissioning Project
Kee-Way-Win First Nation -
Sachigo Lake First Nation - Lot Servicing for future houses
Sachigo Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Kingfisher Lake PoP -
Sachigo Lake First Nation Wastewater Treatment Project
Sachigo Lake First Nation -
Teacherages Project (Site Servicing)
Poplar River First Nation -
Poplar River First Nation School
Poplar River Manitoba School -
Project 4 — All-Season Road Connecting Berens River to Poplar River First Nation
-
Poplar River Bridge Replacement
Poplar River First Nation -
Poplar River First Nation Lagoon Expansion
Poplar River First Nation -
Poplar River First Nation - Community Wharf - 2022/2023
Poplar River First Nation -
Poplar River - Harbour Improvements
Poplar River -
Poplar River Harbour Manitoba - Routine Maintenance Dredging of the Poplar River at Lake Winnipeg - Winter 2019
Poplar River Harbour -
New Fibre Installation / Upgrade Multiple Towers
Weagamow PoP -
New Fibre Installation / Upgrade Multiple Towers
Deer Lake PoP -
New Fibre Installation
North Spirit Lake -
Poplar River First Nation
Poplar River First Nation -
Norway House Cree Nation Business Center
Norway House Cree Nation -
Norway House Cree Nation Water Intake Replacement and Lagoon Cell Decommissioning
Norway House Cree Nation -
New Fibre Installation / Upgrade Multiple Towers
Kewaywin PoP