Fortis Alberta 610013030 Castle Junction 551L Rebuild

FortisAlberta is proposing to replace part of the 551L line, from Castle junction to Silver city, as the structure is nearing the end of its' structural integrity. In total 1.6km of line will be rebuilt. The new line will be placed adjacent to the existing infrastructure within the RoW, in order for the power cables to be transferred over. The project would like to commence in September and will take 3 weeks to complete.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Latest update

July 29, 2022 – Parks Canada intends to make a determination regarding whether the carrying out of the project is likely to cause significant adverse environmental effects. To help inform this determination, Parks Canada is inviting public comments until August 28, 2022 respecting that determination.

Key documents

Key documents
Document Number Document Title File Date
1 New project being assessed by Parks Canada - Public comments invited from July 29 to August 28, 2022 - July 29, 2022

List all records

Contacts

Banff National Park
Box 900
Banff, Alberta T1L 1K2
Telephone: 403-762-1419
Email: anna.brown@pc.gc.ca


  • Location

    • Banff National Park of Canada (Alberta)
  • Nature of Activity

    • Hydroelectric Energy
  • Assessment Status

    In progress
  • Start Date

    2022-07-29
  • Proponent

    FortisAlberta
  • Authorities

    • Parks Canada Agency
  • Assessment Type

    Project on federal lands
  • Reference Number

    83865