Construction of 25KV distribution powerline to IPC Canada Site 13-35-19-7-4

Fortis Alberta to construct a 25 kV 3-phase distribution power line 810 km. The proposed tap will be starting from 8-3-20-7-4 to existing IPC site 13-35-19-7-4. The proposed tap will be fed from an existing line 25 kV phase line.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Latest update

August 9, 2022 – The public comment period on the project is closed. The Department of National Defence is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.

List all records

Contacts

Department of National Defence
Danny Laganiere, Base Environmental Officer, CFB Suffield
CFB Suffield, Post Office Box 6000 Station Main
Medicine Hat, Alberta T1A 8K8
Email: Danny.Laganiere@forces.gc.ca

FortisAlberta
Tim Tea, Designer
FortisAlberta
1301 Dirkson Drive NE
Redcliff, Alberta T0J 2P0
Telephone: 403-502-3106
Email: Tim.Tea@fortisAlberta.com


  • Location

    • Canadian Forces Base (CFB) Suffield (Alberta)
  • Nature of Activity

    • Oil and Gas
  • Assessment Status

    In progress
  • Start Date

    2022-07-20
  • Proponent

    FortisAlberta
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands