Document Notice of Determination

  • Project Demolition of Existing and Construction of New Building (WP100) - 5th Canadian Division Support Base, Gagetown
  • Document Category: Additional Information
  • Reference Number: 2
  • Updated: 2023-01-09
  • Document: 146013E.html
  • Relevance: 355.18
  • Notice of Determination January  9, 2023 – 5th Canadian Division Support Base, Gagetown The Department of National Defence has determined that the proposed ‘Demolition of Existing and Construction of New Building (WP100)' project is not likely to cause significant adverse environmental effects. This determination was based on a consideration of the following factors: impacts on rights of Indigenous peoples; Indigenous knowledge; community knowledge; comments received from the ...
1 alternate format found
French HTML
  • Relevance: 304.18
  • Avis de détermination Le 9 janvier 2023 – Base de soutien de la 5e Division du Canada, Gagetown Le Ministère de la Défense nationale a déterminé que le projet proposé ‘Démolition de l'existant et construction d'un nouveau bâtiment (WP100)' n'est pas susceptible de causer des effets négatifs importants sur l'environnement. La décision est fondée sur l'examen des facteurs suivants : répercussions sur les droits des peuples autochtones; connaissances autochtones; connaissances ...

Document Public Comment Period on Intent to Make a Determination

  • Project Demolition of Existing and Construction of New Building (WP100) - 5th Canadian Division Support Base, Gagetown
  • Document Category: For Public Participation
  • Reference Number: 1
  • Updated: 2022-12-10
  • Document: 145740E.html
  • Relevance: 352.3
  • Public Comment Period on Intent to Make a Determination Demolition of Existing and Construction of New Building (WP100) – 5th Canadian Division Support Base, Gagetown December 10, 2022 — The Department of National Defence must decide whether the proposed project is likely to cause significant adverse environmental effects. To help inform this decision, the Department of National Defence is inviting comments from the public on the project and its potential effects on the environment. All ...
1 alternate format found
French HTML
  • Relevance: 301.3
  • Période de rétroaction du public sur l'avis d'intention de procéder à une détermination Démolition de l'existant et construction d'un nouveau bâtiment (WP100) – Base de soutien de la 5e Division du Canada, Gagetown Le 10 décembre 2022 — Ministère de la Défense nationale doit déterminer si le projet proposé est susceptible d'entraîner des effets négatifs importants sur l'environnement. Afin de contribuer à une prise de détermination éclairée, le Ministère de la Défense nationale invite le ...

Refine SearchDisplay Filters

Last UpdatedDisplay Filters

Filters

Result Type Display Filters

Date modified: