Document Notice of Determination

  • Project Construction of Distribution Powerline to IPC Canada 8-27-19-8-4
  • Document Category: Additional Information
  • Reference Number: 2
  • Updated: 2022-10-25
  • Document: 145359E.html
  • Relevance: 345.98
  • Notice of Determination October 25, 2022 – Canadian Forces Base (CFB) Suffield The Department of National Defence has determined that the proposed ‘Construction of Distribution Powerline to IPC Canada 8-27-19-8-4' project is not likely to cause significant adverse environmental effects. This determination was based on a consideration of the following factors: comments received from the public; and technically and economically feasible mitigation measures The Department of National ...
1 alternate format found
French HTML
  • Relevance: 294.98
  • Avis de détermination Le 25 octobre 2022 – Base des Forces canadiennes (BFC) Suffield Le Ministère de la Défense nationale à déterminé que le projet proposé ‘Construction d'une ligne électrique de distribution vers IPC Canada 8-27-19-8-4' n'est pas susceptible de causer des effets négatifs importants sur l'environnement. La décision est fondée sur l'examen des facteurs suivants : commentaires reçus du public; et les mesures d'atténuation réalisables, sur les plans technique et ...

Document Public Comment Period on Intent to Make a Determination

  • Project Construction of Distribution Powerline to IPC Canada 8-27-19-8-4
  • Document Category: For Public Participation
  • Reference Number: 1
  • Updated: 2022-07-11
  • Document: 144392E.html
  • Relevance: 336.26
  • Public Comment Period on Intent to Make a Determination Construction of Distribution Powerline to IPC Canada 8-27-19-8-4 July 11, 2022 — The Department of National Defence must decide whether the proposed project is likely to cause significant adverse environmental effects. To help inform this decision, the Department of National Defence is inviting comments from the public on the project and its potential effects on the environment. All comments received will be considered public. For ...
1 alternate format found
French HTML
  • Relevance: 285.26
  • Période de rétroaction du public sur l'avis d'intention de procéder à une détermination Construction d'une ligne électrique de distribution vers IPC Canada 8-27-19-8-4 Le 11 juillet 2022 — Ministère de la Défense nationale doit déterminer si le projet proposé est susceptible d'entraîner des effets négatifs importants sur l'environnement. Afin de contribuer à une prise de détermination éclairée, le Ministère de la Défense nationale invite le public à formuler des commentaires sur cette ...