Construction and Operation of a new Gas Hut - Canadian Forces Base Borden

Registry Search Mobile

Registry Search

Skip to Filters

4 results

Document Notice of Determination

  • Project Construction and Operation of a new Gas Hut - Canadian Forces Base Borden
  • Document Category: Additional Information
  • Reference Number: 2
  • Updated: 2022-05-06
  • Document: 143749E.html
  • Relevance: 332.26
  • Notice of Determination May 6, 2022 – Canadian Forces Base Borden The Department of National Defence has determined that the proposed ‘Construction and Operation of a new Gas Hut' project is not likely to cause significant adverse environmental effects. This determination was based on a consideration of the following factors: impacts on rights of Indigenous peoples; comments received from the public; and technically and economically feasible mitigation measures The Department of ...
1 alternate format found
French HTML
  • Relevance: 281.26
  • Avis de détermination Le 6 mai 2022 – Base des Forces canadiennes Borden Le Ministère de la Défense nationale a déterminé que le projet proposé ‘Construction et exploitation d'une nouvelle chambre à gaz' n'est pas susceptible de causer des effets négatifs importants sur l'environnement. La décision est fondée sur l'examen des facteurs suivants : répercussions sur les droits des peuples autochtones; commentaires reçus du public; et les mesures d'atténuation réalisables, sur les plans ...

Document Public Comment Period on Intent to Make a Determination

  • Project Construction and Operation of a new Gas Hut - Canadian Forces Base Borden
  • Document Category: For Public Participation
  • Reference Number: 1
  • Updated: 2022-03-18
  • Document: 143242E.html
  • Relevance: 327.95
  • Public Comment Period on Intent to Make a Determination Construction and Operation of a new Gas Hut – Canadian Forces Base Borden March 18, 2022 — The Department of National Defence must decide whether the proposed project is likely to cause significant adverse environmental effects. To help inform this decision, the Department of National Defence is inviting comments from the public on the project and its potential effects on the environment. All comments received will be considered ...
1 alternate format found
French HTML
  • Relevance: 276.95
  • Période de rétroaction du public sur l'avis d'intention de procéder à une détermination Construction et exploitation d'une nouvelle chambre à gaz – Base des Forces canadiennes Borden Le 18 mars 2022 — Ministère de la Défense nationale doit déterminer si le projet proposé est susceptible d'entraîner des effets négatifs importants sur l'environnement. Afin de contribuer à une prise de détermination éclairée, le Ministère de la Défense nationale invite le public à formuler des commentaires ...

Refine SearchDisplay Filters

Last UpdatedDisplay Filters

Filters

Result Type Display Filters

Date modified: