Document Notice of Determination on Time Limit Extension Request

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 152
  • Updated: 2022-04-06
  • Document: 143507E.html
  • Relevance: 340.53
  • Notice of Determination on Time Limit Extension Request Ottawa – April 6, 2022 – On April 6, 2022, the Impact Assessment Agency of Canada (the Agency) granted an extension to the three-year time limit for Suncor Energy Inc. (the Proponent) to provide the required information or studies described in the Final Tailored Impact Statement Guidelines, and any subsequent modifications, for the impact assessment of the Suncor Base Mine Extension Project. The Agency has taken this action further to ...
1 alternate format found
French HTML
  • Relevance: 289.53
  • Avis de décision sur la demande de prolongation du délai Ottawa, le 6 avril 2022 – L'Agence d'évaluation d'impact du Canada (l'Agence) a accordé à Suncor Energy Inc. (le promoteur) une prolongation du délai de trois ans pour fournir les études ou renseignements requis décrits dans la version finale des Lignes directrices adaptées à l'étude d'impact, ainsi que dans toutes modifications subséquentes, pour l'évaluation d'impact du Projet d'agrandissement de la mine Base de Suncor L'Agence a ...

Document From Chard Métis Nation to the Impact Assessment Agency of Canada re: Chard Métis Nation's Preliminary Traditional Land Use Study: Suncor Base Mine Expansion Project

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 149
  • Updated: 2021-08-24
  • Document: 141237E.pdf
  • Relevance: 320.69
  • Claudette Bois                                                                ...

Document Permitting Plan

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 141
  • Updated: 2021-05-31
  • Document: 139240E.pdf
  • Relevance: 313.59
  • Permitting Plan IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT May 31, 2021 IMPACT ASSESSMENT AG ENCY OF CANADA PERMITT ING PLAN 1 Permitting Plan SUNCOR BASE MINE EXTENSION PROJECTSUNCOR ENERGY INC. May 31, 2021 1. Introduction On August 7, 2020 the Impact Assessment Agency of Canada (the Agency) determined that an impact assessment is required for the Suncor Base Mine Extension ...
1 alternate format found
English HTML
  • Relevance: 313.59
  • Permitting Plan Impact Assessment of the Suncor Base Mine Extension Project May 31, 2021 1. Introduction On August 7, 2020 the Impact Assessment Agency of Canada (the Agency) determined that an impact assessment is required for the Suncor Base Mine Extension Project (the Project) pursuant to Subsection 16(1) of the Impact Assessment Act. This Permitting Plan was developed by the Agency to outline the federal permits, licences and authorizations (regulatory instruments) that may be ...

Document Cooperation Plan

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 140
  • Updated: 2021-05-31
  • Document: 139319E.html
  • Relevance: 313.59
  • Cooperation Plan Impact Assessment of the Suncor Base Mine Extension Project May 31, 2021 1. Introduction On August 7, 2020, the Impact Assessment Agency of Canada (the Agency) determined that an impact assessment is required for the Suncor Base Mine Extension Project (the Project), pursuant to Canada's Impact Assessment Act. Likewise, on February 26, 2020, the Alberta Energy Regulator (AER) determined that an environmental impact assessment (EIA) report is required for the Project, ...
1 alternate format found
English PDF
  • Relevance: 313.59
  • Cooperation Plan IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT May 31, 2021 IMPACT ASSESSMENT AGENCY OF CANADA COOPERATION PLAN 1 Cooperation Plan IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT May 31, 2021 1. Introduction On August 7, 2020, the Impact Assessment Agency of Canada (the Agency) determined that an impact assessment is required for the Suncor Base Mine Extension Project (the ...

Document Tailored Impact Statement Guidelines

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 137
  • Updated: 2021-05-31
  • Document: 139236E.pdf
  • Relevance: 313.59
  • Suncor Base Mine Extension Project TAILORED IMPACT STATEMENT GUIDELINES PURSUANT TO THE IMPACT ASSESSMENT ACT May 31, 2021 IMPACT ASSESSMENT AG ENCY OF CANADA TAILORED IMPACT STAT EMENT GUIDELINES - SUNCOR BASE MINE EXTE NSION PROJECT i Contents List of Abbreviations and Acronyms ................................................................................................ iv Glossary ...
1 alternate format found
English HTML
  • Relevance: 313.59
  • Suncor Base Mine Extension Project Tailored Impact Statement Guidelines Pursuant to the Impact Assessment Act May 31, 2021 Contents List of Abbreviations and Acronyms Glossary 1. Introduction 1.1. Factors to be considered in the Impact Assessment 2. Proponent information 2.1. The proponent 2.2. Qualifications of individuals preparing the Impact Statement 3. Project description 3.1. Project overview 3.2. Project location 3.3. Regulatory framework 3.4. Project ...

Document Draft Cooperation Plan

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 85
  • Updated: 2021-03-22
  • Document: 138417E.pdf
  • Relevance: 307.91
  • Draft Cooperation Plan IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT March 22, 2021 DRAFT VERSION IMPACT ASSESSMENT AG ENCY OF CANADA DRAFT COOPERATION PL AN 1 Draft Cooperation Plan DRAFT COOPERATION PLAN FOR THE IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT March 22, 2021 1. Introduction On August 7, 2020, the Impact Assessment Agency of Canada (the Agency) determined that an impact ...
1 alternate format found
English HTML
  • Relevance: 307.91
  • Draft Cooperation Plan Impact Assessment of the Suncor Base Mine Extension Project March 22, 2021 1. Introduction On August 7, 2020, the Impact Assessment Agency of Canada (the Agency) determined that an impact assessment is required for the Suncor Base Mine Extension Project (the Project), pursuant to Canada's Impact Assessment Act. Likewise, on February 26, 2020, the Alberta Energy Regulator (AER) determined that an environmental impact assessment (EIA) report is required for the ...

Document Draft Tailored Impact Statement Guidelines

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 78
  • Updated: 2021-02-26
  • Document: 139254E.html
  • Relevance: 306
  • Suncor Base Mine Extension Project Draft Tailored Impact Statement Guidelines pursuant to the Impact Assessment Act February 26, 2021 DRAFT FOR PUBLIC COMMENT Contents 1. Introduction 1.1. Factors to be considered in the Impact Assessment 2. Proponent information 2.1. The proponent 2.2. Qualifications of individuals preparing the Impact Statement 3. Project description 3.1. Project overview 3.2. Project location 3.3. Regulatory framework 3.4. Project components ...
1 alternate format found
English PDF
  • Relevance: 306
  • Suncor Base Mine Extension Project DRAFT TAILORED IMPACT STATEMENT GUIDELINES PURSUANT TO THE IMPACT ASSESSMENT ACT February 26, 2021 DRAFT FOR PUBLIC COMMENT IMPACT ASSESSMENT AG ENCY OF CANADA TAILORED IMPACT STAT EMENT GUIDELINES - SUNCOR BASE MINE EXTE NSION PROJECT i Contents 1. Introduction ............................................................................................................................... ...

Document Draft Indigenous Engagement and Partnership Plan

  • Project Suncor Base Mine Extension Project
  • Document Category: Additional Information
  • Reference Number: 83
  • Updated: 2021-02-26
  • Document: 138160E.pdf
  • Relevance: 306
  • Draft Indigenous Engagement and Partnership Plan IMPACT ASSESSMENT OF THE SUNCOR BASE MINE EXTENSION PROJECT February 26, 2021 DRAFT VERSION IMPACT ASSESSMENT AGENCY OF CANADA DRAFT INDIGENOUS ENG AGEMENT AND PARTNERS HIP PLAN – DRAFT VERSION 2 Contents Draft Indigenous Engagement and Partnership Plan ....................................... 1 Indigenous Engagement and Partnership Plan ...
1 alternate format found
English HTML
  • Relevance: 306
  • Draft Indigenous Engagement and Partnership Plan Impact Assessment of the Suncor Base Mine Extension Project February 26, 2021 DRAFT VERSION Contents Draft Indigenous Engagement and Partnership Plan Indigenous Engagement and Partnership Plan 1. Introduction 2. Description of the proposed Project 3. Objectives of Indigenous engagement and partnership 4. Indigenous communities 5. Engagement and consultation tools, and methods 6. Distinction between the Review Panel and the Crown ...