Document Notice of Time Limit Extension

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 37
  • Updated: 2022-06-23
  • Document: 144172E.html
  • Relevance: 334.73
  • Notice of Time Limit Extension Ottawa – June 23, 2022 – On June 21, 2022, the Impact Assessment Agency of Canada (the Agency) granted an extension to the three-year time limit for Nova Scotia Lands (the proponent) to provide the required information or studies described in the Final Environmental Impact Statement Guidelines for the environmental assessment of the Boat Harbour Remediation Project. The Agency has taken this action further to a written request from the proponent that the time ...
1 alternate format found
French HTML
  • Relevance: 283.73
  • Avis de prolongation du délai Ottawa – le 23 juin 2022 – Le 21 juin 2022, l'Agence d'évaluation d'impact du Canada (l'Agence) a accordé une prolongation au délai de trois ans pour que Nova Scotia Lands (le promoteur) fournisse l'information ou les études requises dans les lignes directrices finales de l'étude d'impact environnemental pour l'évaluation environnementale du projet de remise en état de Boat Harbour. L'Agence a pris cette mesure suite à une demande écrite du promoteur (en ...

Document Summary of the External Technical Review Report

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 31
  • Updated: 2021-02-10
  • Document: 141420E.pdf
  • Relevance: 293.83
  • BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY Suite 630 - 1718 Argyle Street Halifax, NS Canada B3J 3N6 Telephone (902) 474-5925 Fax (902) 474-5929 February 10, 2021 Project No.: 2155001 Miriam Padolsky, Ph.D. Impact Assessment Agency of Canada Place Bell; 160 Elgin Street Ottawa, Ontario K1A 0H3 Dear Ms. Padolsky, Re: External Technical Review of the Boat Harbour Remediation Project – Plain Language Summary BGC Engineering Inc. is pleased to present this Plain ...
1 alternate format found
French PDF
  • Relevance: 242.83
  • BoatHarbour_ETE_language_simple_10Fev_2021 BGC ENGINEERING INC. Page 1 BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY Suite 630 – 1718 Argyle Street Halifax (Nouvelle-Écosse) Canada B3J 3N6 Téléphone : 902-474-5925 Télécopie : 902-474-5929 10 février 2021 No de projet : 2155001 Miriam Padolsky, PhD Agence d’évaluation d’impact du Canada Bell Place, 160, rue Elgin Ottawa (Ontario) K1A 0H3 Madame Padolsky, ...

Document External Technical Review Report

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 30
  • Updated: 2021-01-29
  • Document: 141419E.pdf
  • Relevance: 292.93
  • BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY IMPACT ASSESSMENT AGENCY OF CANADA BOAT HARBOUR REMEDIATION PROJECT EXTERNAL TECHNICAL REVIEW FINAL PROJECT NO.: 2155001 DATE: January 29, 2021 BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY Suite 630 - 1718 Argyle Street Halifax, NS Canada B3J 3N6 Telephone (902) 474-5925 Fax (902) 474-5929 January 29, 2021 Project No.: 2155001 Miriam Padolsky, Ph.D. Impact Assessment Agency of Canada Place ...
1 alternate format found
French PDF
  • Relevance: 241.93
  • BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY AGENCE D’ÉVALUATION D’IMPACT DU CANADA PROJET DE REMISE EN ÉTAT DE BOAT HARBOUR EXAMEN TECHNIQUE EXTERNE VERSION FINALE PROJET No : 2155001 DATE : 29 janvier 2021 BGC ENGINEERING INC. AN APPLIED EARTH SCIENCES COMPANY Bureau 630 – 1718, rue Argyle Halifax (N.-É.) Canada B3J 3N6 Téléphone : 902 474-5925 Télécopieur : 902 474-5929 Le 29 janvier 2021 Projet no : 2155001 Miriam Padolsky, Ph. D. ...

Document Public Notice - Public Comments Invited on a Summary of the Environmental Impact Statement

  • Project Boat Harbour Remediation Project
  • Document Category: For Public Participation
  • Reference Number: 19
  • Updated: 2020-12-17
  • Document: 137176E.html
  • Relevance: 289.77
  • Public Notice Boat Harbour Remediation Project — Public Comments Invited What is happening? December 17, 2020 – The Impact Assessment Agency of Canada (the Agency) is conducting a federal environmental assessment for the proposed Boat Harbour Remediation Project, located next to Pictou Landing First Nation and five kilometres east of Pictou, Nova Scotia. The public and Indigenous groups are invited to comment on the potential environmental effects of the project and the proposed measures ...
1 alternate format found
French HTML
  • Relevance: 238.77
  • Avis public Projet de remise en état Boat Harbour — Période de consultation publique Que se passe-t-il? Le 17 décembre 2020 — L'Agence d'évaluation d'impact du Canada (l'Agence) réalise une évaluation environnementale fédérale pour le projet de remise en état Boat Habour, situé à côté de la Première Nation de Pictou Landing et cinq kilomètres à l'est de Pictou, en Nouvelle-Écosse. Le public et les groupes autochtones sont invitées à formuler des commentaires sur les effets ...

Document News Release - Public Comments Invited on a Summary of the Environmental Impact Statement

  • Project Boat Harbour Remediation Project
  • Document Category: News Releases
  • Reference Number: 20
  • Updated: 2020-12-17
  • Document: 137177E.html
  • Relevance: 289.77
  • News Release Boat Harbour Remediation Project — Public Comments Invited December 17, 2020 — Ottawa — Impact Assessment Agency of Canada The Impact Assessment Agency of Canada (the Agency) is conducting a federal environmental assessment for the proposed Boat Harbour Remediation Project, located next to Pictou Landing First Nation and five kilometres east of Pictou, Nova Scotia. The public and Indigenous groups are invited to comment on the potential environmental effects of the project ...
1 alternate format found
French HTML
  • Relevance: 238.77
  • Communiqué Projet de remise en état Boat Harbour — Période de consultation publique Le 17 décembre 2020 — Ottawa — Agence d'évaluation d'impact du Canada L'Agence d'évaluation d'impact du Canada (l'Agence) réalise une évaluation environnementale fédérale pour le projet de remise en état Boat Harbour, situé à côté de la Première Nation de Pictou Landing et cinq kilomètres à l'est de Pictou, en Nouvelle-Écosse. Le public et les groupes autochtones sont invitées à formuler des commentaires ...

Document Public Notice - Federal Funding Allocated to Participate in the Environmental Assessment

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 18
  • Updated: 2020-12-03
  • Document: 137081E.html
  • Relevance: 288.75
  • Boat Harbour Remediation Project - Participant Funding Allocated The Impact Assessment Agency of Canada allocated federal funds to the following recipient to assist their participation in specific activities related to the environmental assessment for this proposed project. Details of Funding Allocation for the Project Recipient Total Funding Allocation Pictou Landing First Nation on behalf of the Assembly of Nova Scotia Mi'kmaw ...
1 alternate format found
French HTML
  • Relevance: 237.75
  • Projet de remise en état de Boat Harbour - Attribution d'une aide financière à un participant L'Agence d'évaluation d'impact du Canada a attribué de l'aide financière fédérale au bénéficiaire suivant pour favoriser leur participation à des activités précises liées à l'évaluation environnementale pour ce projet. Répartition de l'aide financière pour le projet Bénéficiaire Montant attribué Pictou Landing First Nation au nom de Assembly of Nova Scotia Mi'kmaw ...

Document Summary of the Environmental Impact Statement

  • Project Boat Harbour Remediation Project
  • Document Category: For Public Participation
  • Reference Number: 21
  • Updated: 2020-11-27
  • Document: 137217E.pdf
  • Relevance: 288.31
  • Summary of the Environmental Impact Statement Boat Harbour Remediation Project Pictou Landing, Nova Scotia Nova Scotia Lands Inc. November 27, 2020 GHD | Summary of Environmental Impact Statement | Page i Table of Contents 1. Introduction and Environmental Impact Assessment Context ..................................................... 1 2. Project Overview ...
1 alternate format found
French PDF
  • Relevance: 237.31
  • Résumé de l'étude d'impact environnemental Le projet de remise en état de Boat Harbour Pictou Landing, Nouvelle-Écosse Nova Scotia Lands Inc. November 27, 2020 GHD | Énoncé de l'étude d'impact environnemental | Page i Table des matières 1. Introduction et contexte de l'étude d'impact environnemental ..................................................... 1 2. Aperçu du projet ...

Document Notice of an External Technical Review

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 17
  • Updated: 2020-11-17
  • Document: 136734E.html
  • Relevance: 287.59
  • Notice of an External Technical Review Ottawa — November 17, 2020 — The Impact Assessment Agency of Canada will be performing an External Technical Review (ETR) with respect to certain elements of the Boat Harbour Remediation Project's Environmental Impact Statement to analyze: the proponent's information and analysis for identifying alternative means and selecting the preferred alternative including the technical and economic feasibility of the alternative means considered; and the ...
1 alternate format found
French HTML
  • Relevance: 236.59
  • Avis d'examen technique externe Ottawa — 17 novembre 2020 — L'Agence d'évaluation d'impact du Canada lancera un examen technique externe relatif à certains éléments de l'étude d'impact environnemental du projet de remise en état de Boat Harbour dans le but d'analyser : les renseignements qu'a fournis le promoteur et son analyse en ce qui concerne la détermination de solutions de rechange et le choix de la solution privilégiée, y compris la faisabilité technique et économique de ces ...

Document Public Notice - Federal Funding Available

  • Project Boat Harbour Remediation Project
  • Document Category: For Public Participation
  • Reference Number: 12
  • Updated: 2019-11-01
  • Document: 133002E.html
  • Relevance: 262.23
  • Public Notice Boat Harbour Remediation Project — Participant Funding Available November 1, 2019 — The Impact Assessment Agency of Canada (the Agency) is making funding available through its Participant Funding Program to assist the participation of the public and Indigenous groups in the federal environmental assessment for the proposed Boat Harbour Remediation Project, located next to Pictou Landing First Nation, Pictou, Nova Scotia. Funding is available for eligible individuals and ...
1 alternate format found
French HTML
  • Relevance: 211.23
  • Avis public Projet de remise en état de Boat Harbour — Disponibilité d'une aide financière aux participants Le 1er novembre 2019 — L'Agence d'évaluation d'impact du Canada annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des groupes autochtones à l'évaluation environnementale fédérale du projet de remise en état de Boat Harbour, situé à côté de la Première Nation de Pictou ...

Document News Release - Federal Funding Allocated to Participate in the Environmental Assessment

  • Project Boat Harbour Remediation Project
  • Document Category: News Releases
  • Reference Number: 11
  • Updated: 2019-11-01
  • Document: 133001E.html
  • Relevance: 262.23
  • News Release Boat Harbour Remediation Project — Participant Funding Available November 1, 2019 — Ottawa — Impact Assessment Agency of Canada The Impact Assessment Agency of Canada (the Agency) is making funding available through its Participant Funding Program to assist the participation of the public and Indigenous groups in the federal environmental assessment for the proposed Boat Harbour Remediation Project, located next to Pictou Landing First Nation, Pictou, Nova Scotia. Funding is ...
1 alternate format found
French HTML
  • Relevance: 211.23
  • Communiqué Projet de remise en état de Boat Harbour — Disponibilité d'une aide financière aux participants Le 1er novembre 2019 — Ottawa — Agence d'évaluation d'impact du Canada L'Agence d'évaluation d'impact du Canada annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des groupes autochtones à l'évaluation environnementale fédérale du projet de remise en état de Boat Harbour, ...

Document Final Environmental Impact Statement Guidelines

  • Project Boat Harbour Remediation Project
  • Document Category: Additional Information
  • Reference Number: 10
  • Updated: 2019-05-31
  • Document: 143775E.html
  • Relevance: 253.25
  • Guidelines For the Preparation Of An Environmental Impact Statement Pursuant to the Canadian Environmental Assessment Act, 2012 Boat Harbour Remediation Project Nova Scotia Lands Inc. May 2019 Table of Contents Guidelines For the Preparation Of an Environmental Impact Statement Disclaimer Abbreviations and Short Forms Part 1 - Key Considerations 1. Introduction 2. Guiding Principles 2.1 Environmental assessment as a planning and decision making tool 2.2 Public ...
3 alternate formats found
English PDF
  • Relevance: 253.25
  • GUIDELINES FOR THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT pursuant to the Canadian Environmental Assessment Act, 2012 BOAT HARBOUR REMEDIATION PROJECT NOVA SCOTIA LANDS INC. May 2019 Boat Harbour Remediation Project: EIS Guidelines ii TABLE OF CONTENTS GUIDELINES FOR THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT ................................ I DISCLAIMER ...
French PDF
  • Relevance: 202.25
  • LIGNES DIRECTRICES POUR LA PRÉPARATION D’UNE ÉTUDE D’IMPACT ENVIRONNEMENTAL réalisée en vertu de la Loi canadienne sur l’évaluation environnementale (2012) PROJET DE REMISE EN ÉTAT DE BOAT HARBOUR NOVA SCOTIA LANDS INC. Mai 2019 Projet de remise en état de Boat Harbour: Lignes directrices pour la préparation d’une étude d’impact environnemental ii TABLE DES MATIÈRES LIGNES DIRECTRICES POUR LA PRÉPARATION D’UNE ÉTUDE D’IMPACT ENVIRONNEMENTAL ...
French HTML
  • Relevance: 202.25
  • Lignes directrices pour la préparation d'une étude d'impact environnemental Réalisée en vertu de la Loi canadienne sur l'évaluation environnementale (2012) Projet de remise en État de Boat Harbour Nova Scotia Lands Inc. Mai 2019 Table des matières Lignes directrices pour la préparation d'une étude d'impact environnemental Avertissement Abréviations et formes abrégées Partie 1 – Considérations principales 1. Introduction 2. Principes directeurs 2.1 Évaluation environnementale ...

Document Draft Environmental Impact Statement Guidelines

  • Project Boat Harbour Remediation Project
  • Document Category: For Public Participation
  • Reference Number: 8
  • Updated: 2019-04-10
  • Document: 129597E.html
  • Relevance: 250.43
  • Draft Guidelines for the Preparation of an Environmental Impact Statement Pursuant to the Canadian Environmental Assessment Act, 2012 Boat Harbour Remediation Project Nova Scotia Lands Inc. April 2019 Table of Contents Draft Guidelines For The Preparation Of An Environmental Impact Statement Disclaimer Abbreviations and Short Forms Part 1 - Key Considerations 1. Introduction 2. Guiding Principles 2.1 Environmental assessment as a planning and decision making tool 2.2 ...
2 alternate formats found
English PDF
  • Relevance: 250.43
  • DRAFT GUIDELINES FOR THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT pursuant to the Canadian Environmental Assessment Act, 2012 BOAT HARBOUR REMEDIATION PROJECT NOVA SCOTIA LANDS INC. April 2019 Boat Harbour Remediation Project: Draft EIS Guidelines ii TABLE OF CONTENTS DRAFT GUIDELINES FOR THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT .................... I DISCLAIMER ...
French HTML
  • Relevance: 199.43
  • Lignes directrices provisoires pour la préparation d'une étude d'impact environnemental Réalisée en vertu de la Loi canadienne sur l'évaluation environnementale (2012) Projet de remise en état de Boat Harbour Nova Scotia lands inc. Avril 2019 Table des matières Lignes directrices provisoires pour la préparation d'une étude d'impact environnemental Avertissement Abréviations et formes abrégées Partie 1 – considérations principales 1. Introduction 2. Principes directeurs 2.1 ...

Document News Release - Public Comments Invited on the Draft Environmental Impact Statement Guidelines

  • Project Boat Harbour Remediation Project
  • Document Category: News Releases
  • Reference Number: 7
  • Updated: 2019-04-10
  • Document: 128138E.html
  • Relevance: 250.43
  • News Release Boat Harbour Remediation Project — Public Comments Invited April 10, 2019 — Ottawa — Canadian Environmental Assessment Agency The Canadian Environmental Assessment Agency (the Agency) has commenced a federal environmental assessment for the Boat Harbour Remediation Project, located next to Pictou Landing First Nation, Pictou, Nova Scotia. The Agency invites the public and Indigenous groups to comment on which aspects of the environment may be affected by this project and ...
1 alternate format found
French HTML
  • Relevance: 199.43
  • Communiqué Projet de remise en état de Boat Harbour — Période de consultation publique Le 10 avril 2019 — Ottawa — Agence canadienne d'évaluation environnementale L'Agence canadienne d'évaluation environnementale (l'Agence) a entamé une évaluation environnementale fédérale pour le projet de remise en état de Boat Harbour, située près de la Première Nation de Pictou Landing, à Pictou, en Nouvelle-Écosse. L'Agence invite le public et les groupes autochtones à formuler des commentaires à ...