Notice of Determination

Ottawa - September 24, 2021 – Infrastructure Canada (INFC) and Fisheries and Oceans Canada (DFO) have determined that the proposed Vaughan Bridge Replacement Project (the Project), in the village of St-Martin's, New Brunswick:

  • Is not likely to cause significant adverse environmental effects

This determination was based on a consideration of the following factors:

  • Impacts on rights of Indigenous peoples;
  • Indigenous knowledge;
  • Community knowledge;
  • Comments received from the public; and
  • Technically and economically feasible mitigation measures.

INFC and DFO are satisfied that the carrying out of the project is not likely to cause significant adverse environmental effects.

Therefore, INFC and DFO may carry out the Project, exercise any power, perform any duty or function, or provide financial assistance to enable the Project to be carried out in whole or in part.