From the Canadian Environmental Assessment Agency to BP Canada Energy Group ULC re: Conformity of further elaboration on response to Information Request IR-114 (see reference document # 30)

PDF Version 65 KB

Document Reference Number: 33

Canadian Environmental Assessment Agency
1801 Hollis Street Suite 200
Halifax, Nova Scotia
B3J 3N4

Agence canadienne d'évaluation environnementale
1801, rue Hollis, bureau 200
Halifax (Nouvelle-Écosse)
B3J 3N4

August 14, 2017

Agency File: 80109

Ms. Anita Perry
Regional Manager, Nova Scotia
BP Canada Energy Group ULC
10th Floor, Founders Square
1701 Hollis Street
Halifax NS B3J 3M8

Dear Ms. Perry:

SUBJECT: Scotian Basin Exploration Drilling Project - Response to Information Request (IR) 114

Dear Ms. Perry:

Thank you for the additional information you provided on August 2, 2017 to the Canadian Environmental Assessment Agency's request for further elaboration of BP's earlier response to Information Request (IR) 114. That IR was about potential effects of the Scotian Basin Exploration Drilling Project on current use of lands and resources for traditional purposes, and on socio-economic conditions in Indigenous communities.

The Agency has completed its conformity review of the new information and has determined that it provides the requested information. The Agency will now conduct a technical review of the response, after which I will advise you if further information is required.

Upon transmission of this letter, and consistent with the Agency's Operational Policy Statement: Information Requests and Timelines (https://www.canada.ca/en/environmental-assessment-agency/news/media-room/media-room-2016/information-requests-timelines.html) the legislated environmental assessment timeline will resume.

Please contact me if you require further information.

Yours truly,

<Original signed by>

Derek McDonald, P.Eng.
Project Manager

c.c.: J. Ray, CNSOPB

Date modified: